The World Bank Report No: ISR14734 Implementation Status & Results Vietnam Second Transmission and Distribution Project (P084871) Public Disclosure Copy Operation Name: Second Transmission and Distribution Project (P084871) Project Stage: Implementation Seq.No: 10 Status: ARCHIVED Archive Date: 21-Jun-2014 Country: Vietnam Approval FY: 2006 Product Line: IBRD/IDA Region: EAST ASIA AND PACIFIC Lending Instrument: Specific Investment Loan Implementing Agency(ies): National Transmission Corporation Key Dates Board Approval Date 28-Jul-2005 Original Closing Date 31-Dec-2010 Planned Mid Term Review Date 30-Sep-2008 Last Archived ISR Date 02-Aug-2013 Effectiveness Date 31-May-2006 Revised Closing Date 30-Jun-2014 Actual Mid Term Review Date 31-May-2009 Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the project is the efficient development of Vietnam's transmission and distribution system. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Transmission and distribution systems expansion and reinforcement 679.57 Electricity market and system operations modernization 22.80 Market transition support 2.15 Overall Ratings Previous Rating Current Rating Moderately Satisfactory Moderately Satisfactory Public Disclosure Copy Progress towards achievement of PDO Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview The project is on track to meeting most of its development objectives of supporting the efficient development of Vietnam's transmission and distribution system. There is a high likelihood that the PDO will be achieved by the project closing date with significant contributions already made to improvements to the efficiency of the transmission and distribution system and with the accomplishment of the structural and institutional goals of unbundling and establishing the transmission business in a separate subsidiary. There will likely be some shortfalls in that the objective of replacing the SCADA system in NLDC which is intended to improve system dispatch efficiency will only be achieved when the related investments are completed after the project closing date and so will two transmission and distribution sub projects. The project finances a total of 24 sub-projects including the construction of power transmission and distribution lines and substations of 500kV, 220kV and 110kV. 22 sub-projects out of 24 sub-projects are either completed or will be Page 1 of 6 The World Bank Report No: ISR14734 completed by June 30, 2014 and the remaining 2 sub-projects are in advanced stage of implementation, but will be completed only after the project has closed. Key performance indicators for the PDO remain relevant and useful in assessing progress towards achieving the PDO. The majority of the indicators have already been achieved and/or exceeded the targets. These confirm that the project has contributed to increasing the overall system efficiency and to improvement of reliability and quality of transmission and distribution service, as demonstrated by: (i) increased new generation capacity (2,250MW compared to target of 1,200MW) connected via 500kV transmission system links financed by the project; (iii) Public Disclosure Copy reduced number and duration of interruptions in 500kV, 220kV and 110kV - as of May 30, 2013, the number and duration of interruptions in 500kV and 220kV systems was reduced to 0.23 – 11.5 hours and 0.47 – 17.18 hours respectively compared to the target of 0.3 – 13.5 hours and 0.45 – 23.8 hours; and (iiii) stabilized actual peak hour minimum voltage measured at 220kV and 110kV system weak points. Locations Country First Administrative Division Location Planned Actual Vietnam Not Entered Xom My Xuan Vietnam Tinh Vinh Long Vinh Long Vietnam Tinh Tien Giang Tinh Tien Giang Vietnam Tinh Kon Tum Tinh Kon Tum Vietnam Thanh pho Ho Chi Minh Thanh pho Ho Chi Minh Vietnam Tinh Long An Tan An Vietnam Tinh Binh Dinh Tam Quan Vietnam Thanh Pho Hai Phong Song Mai Vietnam Tinh Quang Ninh Tinh Quang Ninh Vietnam Tinh An Giang Phu Lam Vietnam Tinh Can Tho O Mon Vietnam Thanh pho Ho Chi Minh Nha Be Vietnam Tinh Long An Tinh Long An Public Disclosure Copy Vietnam Tinh Tien Giang Long An Vietnam Tinh Quang Ninh Ha Long Vietnam Thanh pho Ho Chi Minh Thanh pho Ho Chi Minh Vietnam Tinh Can Tho Tinh Can Tho Vietnam Tinh Dong Thap Tinh Dong Thap Vietnam Tinh Quang Binh Dong Hoi Page 2 of 6 The World Bank Report No: ISR14734 Country First Administrative Division Location Planned Actual Vietnam Not Entered Chu Lai Public Disclosure Copy Vietnam Tinh Tien Giang Cai Lay Vietnam Tinh Dac Lak Buon Ma Thuot Vietnam Tinh Thanh Hoa Binh Tan Vietnam Tinh Bac Giang Bac Giang Vietnam Tinh Tien Giang Huyen Cai Lay Vietnam Thanh pho Ho Chi Minh Huyen Nha Be Vietnam Tinh Can Tho Huyen O Mon Vietnam Thu Do Ha Noi Huyen Soc Son Vietnam Tinh Binh Duong Thi Xa Thu Dau Mot Vietnam Tinh Binh Duong Huyen Tan Uyen Vietnam Tinh Binh Duong Huyen Tan Uyen Vietnam Tinh Dong Nai Huyen Vinh Cuu Vietnam Tinh Dong Nai Huyen Thong Nhat Vietnam Tinh Dong Nai Huyen Long Thanh Vietnam Tinh Tien Giang Chau Thanh Vietnam Tinh Bac Giang Doc Soi 500KV Substation Vietnam Tinh Ba Ria-Vung Tau Cam My District Public Disclosure Copy Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Generation capacity connected to 500kV Text Value 0 2250 1200 MW by project close transmission system links financed by project. Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Page 3 of 6 The World Bank Report No: ISR14734 Number and duration of interruptions in the Text Value Interruptions in system, per Interruptions in system per Interruptions in system, per 500kV and 220kV transmission system and 100 circuit km: 500kV: 100 circuit km: 500kV: 100 circuit km: 110kV distribution system number 0.33; duration 15.75 number 0.23; duration 11.5 - 500kV: number 0.3; duration mins. 220kV: number 0.596; mins. 13.5 mins. Public Disclosure Copy duration 21.2 mins. 110kV: -200kV: number 0.47; - 220kV: number 0.45; number3.32; duration 28.8 duration 17.18 mins. duration 23.8 mins. mins -110kV: number 0.103; - 110kV: number 3.166; duration 8.164 mins duration 28.22 mins Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Peak hour minimum voltages at system weak Text Value Peak hour minimum voltage Peak hour minimum voltage Peak hour minimum voltage points (kV): Bac Lieu - 205 Quy (kV): Bac Lieu-222; Quy (kV): Nhon - 210 Soc Trang - 108 Nhon-218: soc Trang-115; Bac Lieu - 225 Trang Bang - 107 Quang Ngai Trang Bang-115; Quang Ngai Quy Nhon - 225 - 109 Mong Cai - 108 -115; Mong Cai-115 Soc Trang - 115 Trang Bang - 115 Quang Ngai - 115 Mong Cai - 115 Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Separate transmission and market system Text Value No separately identifiable Single buyer market operators (TSO and MSO) capable of function TSO or MSO - functions established, TSO/MSO at within single buyer market mainly taken by NLDC arms length from generationand distribution, taking dispatch decisions based on market rules Date 28-Jul-2005 30-May-2013 30-Jun-2014 Comments Intermediate Results Indicators Public Disclosure Copy Page 4 of 6 The World Bank Report No: ISR14734 Indicator Name Core Unit of Measure Baseline Current End Target Additional transmission system assets created Text Value Circuit km tranmission and Circuit km transmission and Circuit km tranmission and distribution lines: 500kV: 0 distribution lines: distribution lines: Public Disclosure Copy 220kV: 0 110kV: 0 -500kV: 225km; - 500kV: 502 km; Transformer capacity MVA -220kV: 152km: - 220kV: 180 km; 500/220kV: 0 220/110kV: 0 -110kV: 2676 transformer Transformer capacity MVA: 110kV/MV:0 capacity MVA - 500/220kV: 2,550; -500/220kV: 1,500; - 220/110kV: 2,500; 220/110kV: 875; - 110kV/MV: 400; -110kV/MV: 216 Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Commissioning of new market and Text Value SCADA/EMS: not in place SCADA/EMS not in place, SCADA/EMS: in place transmission system information and control Vietpool interim market Vietpool interim market Vietpool interim market systems system replacement: not in system replacement not in system replacement: in place place Telecommunications place, telecommunications Telecommunications backbone: not in place backbone not in place backbone: in place Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments The new SCADA/EMS likely to be in place about nine months after project closing date Separation of transmission and market Text Value Transmission is Transmission system and Transmission system and operations from other EVN operations disaggregated among four market system operators are market system operators are companies, all 100% owned separated from other EVN separated from other EVN by EVN. No market operator operations preferably with operations, preferably with in place separate ownership separate ownership arrangements arrangements Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Transmission lines constructed or rehabilitated Kilometers Value 0.00 377.00 682.00 Public Disclosure Copy under the project Date 28-Jul-2005 31-Mar-2014 30-Jun-2014 Comments Circuit of 500kV and 220kV Circuit km of 500kV and transmission lines 220kV transmission lines Transmission lines constructed under the Kilometers Value 0.00 377.00 682.00 project Sub Type Date 28-Jul-2005 30-May-2013 30-Jun-2014 Breakdown Comments Data on Financial Performance (as of 04-Jun-2014) Financial Agreement(s) Key Dates Page 5 of 6 The World Bank Report No: ISR14734 Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P084871 IBRD-80260 Effective 29-Mar-2011 31-May-2011 29-Aug-2011 30-Jun-2014 30-Jun-2014 P084871 IDA-41070 Effective 28-Jul-2005 16-Mar-2006 31-May-2006 31-Dec-2010 30-Jun-2014 Public Disclosure Copy Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P084871 IBRD-80260 Effective USD 180.00 180.00 0.00 149.10 30.90 83.00 P084871 IDA-41070 Effective USD 200.00 200.00 0.00 196.56 15.11 98.00 Disbursement Graph Key Decisions Regarding Implementation Public Disclosure Copy There are no key decisions for disclosure at this time. Restructuring History Level two Approved on 19-Dec-2010 Related Projects P114875-Second Transmission and Distribution Project Additional Financing Page 6 of 6