Procurement Plan for WBADMI Project (P105311) I. General 1. Bank’s approval Date of the procurement Plan Aug 25 2011 2. Date of General Procurement Notice: May 10 2010 3. Period covered by this procurement plan: The procurement period of project covered from year 1st June 2011 to 31st May 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above 1000 000 LIB above 200 000 2. NCB (Goods) >50 000 & < 1000 000 3. NCB (Non-Consultant Services) Do 4. ICB (Works) Above 5000 000 5. NCB (Works) Upto 5000 000 6. National shopping < 50 000 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project is using a procurement manual, which is agreed with World Bank 5. Any Other Special Procurement Arrangements: Retroactive financing is applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of Nil - no - - the ICB (Works) July 9, 2010 Summary of Nil Nil the ICB (Goods) Summary of 22 150 no post 10 pkgs the NCB are (Works) through shopping Summary of Nil All goods the NCB are (Goods) through shopping (75 pkgs) Summary of Nil Nil the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 300,000 2. Single Source (Firms) Above USD 100 000 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Retroactive financing applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 1.4 4 - All post number of review contracts that will be let under QCBS Summary of 5.5 4 Prior Two Post number of review contracts that July 9, 2010 will be let under other methods July 9, 2010 PROCUREMENT India : IN West Bengal Accelerated Development of Minor Irrigation PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-07-26 2019-08-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P105311 GPN Date: Project Name: IN West Bengal Accelerated Development of Minor Irrigation Loan / Credit No: IBRD / 80900 Executing Agency(ies): DPMU - Darjeeling WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPMU - DARJEELING- 20093-CW-RFB / Restoration Pending Component B. Irrigation Single Stage - One & repair works of DPMU , IBRD / 80900 Post Request for Bids Open - National 2,221.74 0.00 Implementati 2017-07-11 2017-07-16 2017-08-27 2017-09-26 2017-10-31 2018-04-29 System Development Envelope Darjeeling office building on under WBADMI Project. IN-DPMU - DARJEELING- 20100-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 84,241.03 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Uttar System Development Envelope on Bansgaon Kismat mouza, Phansidewa G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Uttar Ban IN-DPMU - DARJEELING- 20110-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 84,241.03 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Uttar System Development Envelope on Bansgaon Kismat mouza, Phansidewa G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Uttar Ban IN-DPMU - DARJEELING- 20114-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 84,241.03 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Madhya System Development Envelope on Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon-VI Page 1 IN-DPMU - DARJEELING- 20116-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 84,241.03 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Madhya System Development Envelope on Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon-IX IN-DPMU - DARJEELING- 20117-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 84,241.03 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Madhya System Development Envelope on Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon-XI IN-DPMU - DARJEELING- 20118-CW-RFB / Construction and installation including supply ,electrical works and energisation of 4 Under nos.TW(H) at (1 no. TW(H) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 112,290.52 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Madhya System Development Envelope on Bansgaon mouza, Chathat G.P,Phansidewa Block,Darjeeling District under WBADMIP,Name of scheme Madhya Bansgaon-XI IN-DPMU - DARJEELING- 21577-CW-RFB / Construction and installation including supply ,electrical works and energisation of 2 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 50,683.48 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Nipania System Development Envelope on mouza Changa Panighata G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-I TW(E) scheme IN-DPMU - DARJEELING- 21579-CW-RFB / Construction and installation including supply ,electrical works and energisation of 2 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 50,683.48 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Nipania System Development Envelope on mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-II TW(E) schem Page 2 IN-DPMU - DARJEELING- 21581-CW-RFB / Construction and installation including supply ,electrical works and energisation of 2 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 50,683.48 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Nipania System Development Envelope on mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-III TW(E) sche IN-DPMU - DARJEELING- 21582-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Nipania System Development Envelope on mouza Changa Panighata G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-IV TW(E) scheme IN-DPMU - DARJEELING- 21583-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-24 2017-07-29 2017-09-09 2017-10-09 2017-11-13 2018-05-12 cluster structures at Nipania System Development Envelope on mouza Changa Panighata G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-V TW(E) scheme IN-DPMU - DARJEELING- 21584-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 cluster structures at Nipania System Development Envelope on mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VI TW(E) scheme IN-DPMU - DARJEELING- 21585-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 cluster structures at Nipania System Development Envelope on mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VII TW(E) scheme Page 3 IN-DPMU - DARJEELING- 21587-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-28 2017-08-02 2017-09-13 2017-10-13 2017-11-17 2018-05-16 cluster structures at Nipania System Development Envelope on mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-VIII TW(E) scheme IN-DPMU - DARJEELING- 21591-CW-RFB / Construction and installation including supply ,electrical works and energisation of 3 Under nos.TW(E) at (1 no. TW(E) Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 75,693.50 0.00 Implementati 2017-07-27 2017-08-01 2017-09-12 2017-10-12 2017-11-16 2018-05-15 cluster structures at Nipania System Development Envelope on mouza Maniram G.P,Mirik Block,Darjeeling District under WBADMIP,Name of scheme Nipania-IX TW(E) scheme IN-DPMU - DARJEELING- 21594-CW-RFB / Construction and installation including supply ,electrical works and energisation of 2 nos.TW(E) at (1 no. TW(E) Under Component B. Irrigation Single Stage - One cluster structures at IBRD / 80900 Post Request for Bids Open - National 50,683.48 0.00 Implementati 2017-07-27 2017-08-01 2017-09-12 2017-10-12 2017-11-16 2018-05-15 System Development Envelope Rangamohan mouza, Saureni- on II G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Rangamohan-I TW(E) schem IN-DPMU - DARJEELING- 21596-CW-RFB / Construction and installation including supply ,electrical works and energisation of 2 nos.TW(E) at (1 no. TW(E) Under Component B. Irrigation Single Stage - One cluster structures at IBRD / 80900 Post Request for Bids Open - National 50,683.48 0.00 Implementati 2017-07-27 2017-08-01 2017-09-12 2017-10-12 2017-11-16 2018-05-15 System Development Envelope Rangamohan mouza, Saureni- on II G.P,M irik Block,Darjeeling District under WBADMIP,Name of scheme Rangamohan-II TW(E) sche IN-DPMU - DARJEELING- 21599-CW-RFB / Constraction of Elley jhora Pending Component B. Irrigation Single Stage - One SFMI scheme at Mirik IBRD / 80900 Post Request for Bids Open - National 139,892.57 0.00 Implementati 2017-07-26 2017-07-31 2017-09-11 2017-10-11 2017-11-15 2018-05-14 System Development Envelope Khasmahal Mouza, Duptin on GP in Mirik Block,District Darjeeling IN-DPMU - DARJEELING- 21600-CW-RFB / Constraction of Gattey jhora Pending SFMI scheme at Mirik Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 164,470.58 0.00 Implementati 2017-07-25 2017-07-30 2017-09-10 2017-10-10 2017-11-14 2018-05-13 Khasmahal Mouza Pahila System Development Envelope on Gaon School dara II GP in Mirik Block,District Darjeeling Page 4 IN-DPMU - DARJEELING- 92780-CW-RFB / Construction of "Vermicompost production units by using Cement tank Pending & Supply of Earthworms" Component C. Agricultural Single Stage - One IBRD / 80900 Post Request for Bids Open - National 18,033.01 0.00 Implementati 2018-12-26 2018-12-31 2019-02-11 2019-03-13 2019-04-17 2019-10-14 under "Agriculture Support Support Services (ASS) Envelope on Services (Horticulture) Demonstration Programmer" during Rabi, 2018-19 in Kalimpong & Darjeeling District, WBADMI Project IN-DPMU - DARJEELING- 97870-CW-RFB / Construction of Besitar Pending Component B. Irrigation Single Stage - One Jhora SFMI scheme at IBRD / 80900 Post Request for Bids Open - National 50,161.40 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 System Development Envelope Saurini, Saurini-II GP in on Mirik Block,District Darjeeling IN-DPMU - DARJEELING- 98235-CW-RFB / Construction of Bamrang Pending Component B. Irrigation Single Stage - One Jhora SFMI scheme at IBRD / 80900 Post Request for Bids Open - National 63,643.74 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 System Development Envelope Saurini, Saurini-II GP in on Mirik Block,District Darjeeling IN-DPMU - DARJEELING- 98236-CW-RFB / Construction of Najung Pending Component B. Irrigation Single Stage - One Jhora SFMI scheme at IBRD / 80900 Post Request for Bids Open - National 43,891.67 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 System Development Envelope Sakyong Mouza of Sakyong on GP in Kalimpong-II Block,District Kalimpong IN-DPMU - DARJEELING- 98237-CW-RFB / Construction of Bhotay Pending Component B. Irrigation Single Stage - One Khola SFMI scheme at Bong IBRD / 80900 Post Request for Bids Open - National 66,230.92 0.00 Implementati 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 System Development Envelope Khasmahal Mouza of Bong on Khasmahal GP in Kalimpong- I Block,District Kalimpong IN-DPMU - DARJEELING- 105913-CW-RFB / Construction & Installation of Permanent Desi Magur Pending Component D. Project Single Stage - One hatchery shed at Bara IBRD / 80900 Post Request for Bids Open - National 2,616.13 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Management Envelope Chenga,Mirik Block (GTA), on Dist- Darjeeling under DPMU, Darjeeling, WBADMI Project GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-DPMU - DARJEELING- 16669-GO-RFQ / Supply of Agricultural input items of Implementation of Pending Component C. Agricultural Request for Single Stage - One Demonstrats centre IBRD / 80900 Post Open - National 4,262.00 0.00 Implementati 2017-06-05 2017-06-29 2017-12-26 Support Services (ASS) Quotations Envelope programme under ASS on Agriculture & Horticulture during Kharif 2017 under Darjeeling DPMU,WBADMIP Page 5 IN-DPMU - DARJEELING- 18608-GO-RFQ / Supply of Fish fingerlings, Fish feed , other fishery inputs and stationary items for Training Pending Component C. Agricultural Request for Single Stage - One field exposure visit , for IBRD / 80900 Post Open - National 14,940.00 0.00 Implementati 2017-06-26 2017-08-21 2018-02-17 Support Services (ASS) Quotations Envelope implementation of fishery on DC etc. programe under ASS (Fishery) during 2017- 18 under DPMU, Darjeeling, WBADMIP. IN-DPMU - DARJEELING- 20096-GO-RFQ / Supply of Fishery inputs like Fish Fry, Fish Feed, Medicine etc. Pending fingerling production through Component C. Agricultural Request for Single Stage - One IBRD / 80900 Post Limited 1,172.59 0.00 Implementati 2017-07-16 2017-09-10 2018-03-09 SHG under ASS activities Support Services (ASS) Quotations Envelope on (Fishery) DPMU, Darjeeling ,WBADMI Project during 2017-18. (Rearing fry to fingersings) IN-DPMU - DARJEELING- 73887-GO-RFQ / Procurement and Supply of planting Materials of Coffee, Pending Component C. Agricultural Request for Single Stage - One Orange, Black pepper & IBRD / 80900 Post Open - National 30,956.52 0.00 Implementati 2018-08-19 2018-10-14 2019-04-12 Support Services (ASS) Quotations Envelope Large cardamom for the on purpose of kharif plantation programme under WBADMIP during 2018-19 IN-DPMU - DARJEELING- 87773-GO-RFQ / Supply of Vegetable seeds for Implementation of Pending Component C. Agricultural Request for Single Stage - One Demonstration Centre (DC) IBRD / 80900 Post Open - National 27,209.00 0.00 Implementati 2018-11-27 2019-01-22 2019-07-21 Support Services (ASS) Quotations Envelope under ASS activities on (Horticulture) during Rabi 2018-19 under Darjeeling DPMU, WBADMIP. IN-DPMU - DARJEELING- 93932-GO-RFB / Supply of material for the purpose of implementation on Pending Component C. Agricultural Single Stage - One Pisciculture at Nepania and IBRD / 80900 Post Request for Bids Open - National 25,373.97 0.00 Implementati 2019-01-07 2019-01-12 2019-02-23 2019-03-25 2019-04-29 2019-10-26 Support Services (ASS) Envelope Rangmohan Mouza under on Fisheries Activities (C-III) for the current financial year 2018-19 IN-DPMU - DARJEELING- 105901-GO-RFB / Supply of material for Obsetve World Environment day (5th June) as well as Aranya Saptah Component A. Strengthening Pending Single Stage - One (14th -20th July 2018) under IBRD / 80900 Community-based Post Request for Bids Open - National 1,424.11 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Envelope its "Subuj Bangla'' initiative Institutions on responding to climate change and thus contribute in reducing the impact through sensitization and plantat IN-DPMU - DARJEELING- 105902-GO-RFB / Supply of material for Village level Pending Training for the capacity Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 1,819.70 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Building Programme of WUA System Development Envelope on in the District of Darjeeling under WBADMI Project during 2018-19. Page 6 IN-DPMU - DARJEELING- 105907-GO-RFB / Supply of material for Cluster level Pending Training for the capacity Component B. Irrigation Single Stage - One IBRD / 80900 Post Request for Bids Open - National 6,991.11 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Building Programme of WUA System Development Envelope on in the District of Darjeeling under WBADMI Project during 2018-19. IN-DPMU - DARJEELING- 105910-GO-RFB / Supply of computer, Laptop, Printer Pending Component D. Project Single Stage - One etc for camp Office cum IBRD / 80900 Post Request for Bids Open - National 3,387.35 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Management Envelope residence of Darjeeling, on DPMU, WBADMI Project at Kalimpong., 2018-19 IN-DPMU - DARJEELING- 105911-GO-RFB / Supply Of Almirah, Table Chair,etc for Pending Component D. Project Single Stage - One camp Office cum residence IBRD / 80900 Post Request for Bids Open - National 4,257.29 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Management Envelope of Darjeeling, on DPMU,WBADMIProject at Kalimpong., 2018-19 IN-DPMU - DARJEELING- 105912-GO-RFB / Supply of material for the purpose of Two (2 Nos) Technical Workshop with 8(Eight) Pending Project Implementation Component C. Agricultural Single Stage - One IBRD / 80900 Post Request for Bids Open - National 1,004.56 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Unit (PUI) of GTA to Support Services (ASS) Envelope on Implementation for DPMU, Darjeeling and Kalimpong of under WBADMIP during the current financial year 2018- 2019 IN-DPMU - DARJEELING- 105915-GO-RFB / Supply of material for Cluster Level Farmers Training through Pending Component C. Agricultural Single Stage - One FFS under ASS activities IBRD / 80900 Post Request for Bids Open - National 6,116.50 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Support Services (ASS) Envelope (Agriculture & Horticulture) on in the District of Darjeeling under WBADMI Project during Kharif, 2108-19 IN-DPMU - DARJEELING- 105919-GO-RFB / Supply of material for the purpose of Mass production, Exposure Component A. Strengthening Pending Single Stage - One visit, Field day Banner, IBRD / 80900 Community-based Post Request for Bids Open - National 4,866.01 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Envelope implementation under Institutions on Fisheries Activities (C-III) for the current financial year 2018-19 IN-DPMU - DARJEELING- 105922-GO-RFB / Supply of material for the purpose of Component A. Strengthening Pending Single Stage - One implementation under IBRD / 80900 Community-based Post Request for Bids Open - National 6,947.88 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Envelope Fisheries Activities (C-III) at Institutions on Kalimpong for the current financial year 2018-19 IN-DPMU - DARJEELING- 105925-GO-RFB / Supply of material for Exposure Visit, Pending Training for the capacity Component D. Project Single Stage - One IBRD / 80900 Post Request for Bids Open - National 652.94 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Building Programme of WUA Management Envelope on in the District of Darjeeling under WBADMI Project during 2018-19. Page 7 IN-DPMU - DARJEELING- 105926-GO-RFB / Supply of material for Farmers' training, FFS, FFD, Exposure visit (within Pending Component C. Agricultural Single Stage - One district), Workshop under IBRD / 80900 Post Request for Bids Open - National 5,835.99 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 Support Services (ASS) Envelope Capacity Building Program on during Rabi, 2018 under Horticulture activity (2018- 19) WBADMI Project for the FY 2018-19. IN-DPMU - DARJEELING- 105927-GO-RFB / Supply of Vegetable seeds for Implementation of Pending Demonstration Centre (DC) Component C. Agricultural Single Stage - One IBRD / 80900 Post Request for Bids Open - National 6,038.68 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 at Darjeeling District under Support Services (ASS) Envelope on ASS activities (Horticulture) during Pre-kharif, 2018-19 under Darjeeling DPMU, WBADMIP IN-DPMU - DARJEELING- 105928-GO-RFB / Supply of Vegetable seeds for Implementation of Pending Demonstration Centre (DC) Component C. Agricultural Single Stage - One IBRD / 80900 Post Request for Bids Open - National 4,089.80 0.00 Implementati 2019-03-13 2019-03-18 2019-04-29 2019-05-29 2019-07-03 2019-12-30 at Kalimpong District under Support Services (ASS) Envelope on ASS activities (Horticulture) during Pre-kharif, 2018-19 under Darjeeling DPMU, WBADMIP IN-DPMU - DARJEELING- 106523-GO-RFB / Supply of material for Farmers' training, FFS, FFD, Pending Exposure visit (within Component C. Agricultural Single Stage - One IBRD / 80900 Post Request for Bids Open - National 2,144.15 0.00 Implementati 2019-03-17 2019-03-22 2019-05-03 2019-06-02 2019-07-07 2020-01-03 district),Workshop under Support Services (ASS) Envelope on Capacity Building Program during Pre-Kharif, 2019 under Horticulture activity (2018-19) WBADMI Project. IN-DPMU - DARJEELING- 125479-GO-RFQ / Procurement and Supply of of material for the purpose of Mixed Fruit Tree Plantation Programme Pending during Kharif2019 for Component C. Agricultural Request for Single Stage - One IBRD / 80900 Post Open - National 50,038.77 0.00 Implementati 2019-07-30 2019-09-12 2019-12-17 Implementation of Support Services (ASS) Quotations Envelope on Demonstration Centre (DC) under ASS activities(Horticulture) in Kalimpong and Darjeeling district under DPMU Darjeeling NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Page 8 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9