Procurement Plan I. General 1. Project Information Project Name: ENTERPRISE REVITALIZATION AND EMPLOYMENT PILOT (EREP) PROJE Country: Repuplic of yemen Project ID: Loan/Credit Numbers: 2. Bank's approval date of Procurement Plan Original: Revision 1: 3. Date of General Procurement Notice II. Goods, Work and Non-Consulting Services Thresholds 1. Prior Review Threshold. Procurement Decisions subject to Prior Review by the Bank will be as follows Prior Review 1a. Procurement Category Threshold (USD) Goods ≥500,000 Works NA Direct contract Procurement Method Threshold 1b. Procurement Method (USD) ICB (Goods) >= 500,000 NCB (Goods) < 500,000 Shopping (Goods) < = 50,000 ICB (Works) NA NCB (Works) NA NCB (Non-Consultant Services) Include all methods authorized by the loan agreement 2. Prequalification. Bidders for bid NA shall be prequlified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components NA 4. Reference to (if any) Project Operational/Procurement Manual: under approval process 5. Any Other Special Procurement Arrangements: [ncluding advance procurement and retroactive 6. Procurement Packages with Methods and Time Schedule: See attached "Goods and Works" sheet 8/6/2014 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Prior Review 1a. Procurement Category Threshold (USD) Consulting Firms (Competitive) > = 200,000 Consulting Firms (QBS) Individual Consultants (Competitive) > 50,000 Individual Consultants (Sole Source) Consulting Firms (Sole Source) Procurement Method Threshold 1b. Procurement Method (USD) QCBS > = 200,000 QBS <200,000 LCS <200,000 CQS < 200,000 Consulting Firms (Competitive) Consulting Firms (Sole Source) Individual Consultants (Competitive) Individual Consultants (Sole Source) NCB (Non-Consultant Services) Direct Contracting Include all methods authorized by the Grant agreement 2. Note: procurement following DC and SS will be under taken only if these are agreed to by IDA based on OPCPR listfrom justification Note: the project, of ceilings other can be found waise here: acompititive method will be followed. http://go.worldbank.org/MKXO98RY40 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule: See attached "Consulting Services" sheet IV. Implementing Agency Capacity Building Activities with Time Schedule: See attached "Capacity 8/6/2014 NTERPRISE REVITALIZATION AND EMPLOYMENT PILOT (EREP) PROJECT Repuplic of yemen 25-Apr-13 25-Jul-13 ubject to Prior Review by the Bank will be as follows Comments All Contracts+ first two contracts less than the threshold NA Allcontracts Comments All Contracts First two Contracts First two Contracts NA NA First two Contracts lified in accordance with the provisions of paragraphs ement Manual: under approval process ncluding advance procurement and retroactive Schedule: See attached "Goods and Works" sheet 8/6/2014 ect to Prior Review by Bank as stated in Appendix 1 to ltants: Comments All contracts First two Contracts First two contracts All SS contracts All SS contracts Comments under taken only if these are agreed to by IDA based ompititive method will be followed. rldbank.org/MKXO98RY40 uding advance procurement and retroactive financing, ds and Time Schedule: See attached "Consulting with Time Schedule: See attached "Capacity 8/6/2014 EREP Procurement Plan Updated Date: 26/5/2014 Review by Bank (Prior/ Bank for TOR (Date)** forwarded to the Bank Bank to the Technical Country of Contractor Expenses Incurred to Contract Award Date Proposal Submission (incl. Zip Code if US) Advertising for Short Services Completion RFP Final Draft to be Method of Selection No Objection by the No Objection by the Type of Consultant Contract Currency TOR/Shortlist to be Bank for Final RFP RFP Issued (Date) Evaluation Report Contract) (Date)** No Objection from No Objection from No Objection from Bank for Shortlist #Combined/ Draft (Firm/ Individual) Bank (Technical/ Finalized (Date) Deadline (Date) Name, City, and Contract Value Contract/ Final listing (Date) Remarks (Date)** (Date)** (Date)** SL No. Date $ (Date) (Date) Post) Description of Services Prior Individual IC 14/Feb/13 22/Feb/13 N/A 11-Feb-13 24-Feb-13 N/A N/A N/A N/A 05-Apr-13 15-Apr-13 Planned Revised Prior Individual IC 14/Feb/13 22/Feb/13 N/A 11-Feb-13 24-Feb-13 N/A N/A N/A N/A 05-Apr-13 15-Apr-13 Recruitment of Project Manager ‫محمد عبدالخير‬ 1 Prior IC 11/Feb/13 11/Mar/13 N/A 23/Mar/13 28/Mar/13 N/A N/A N/A N/A 29-Apr-13 11-May-13 39,468 $ ‫سالم العويني‬ 5/11/2014 Actual Individual 38,037 completed ‫محمد عبدالخير‬ extension for one year Prior IC N/A N/A N/A N/A N/A N/A N/A N/A N/A 20-May-14 12-May-14 39,468 $ Actual Individual ‫سالم العويني‬ 5/12/2015 0 after the approval of the TTL Planned Post Individual IC N/A 20-May-13 NA 28-May-13 NA NA NA N/A N/A N/A 01-Jul-13 Contracting consultant to Revised Post Individual IC N/A 01-Jul-13 NA 15-Jul-13 NA NA NA N/A N/A N/A 20-Jul-13 20-Aug-13 detremine the CRM specifications 2 and TOR ‫ادريس عبداهلل محمد‬ Extended till 03/04/2014 and Post IC N/A 12-Jun-13 N/A 25-Jun-13 N/A N/A N/A N/A N/A N/A 29-Jun-13 2,000 $ ‫المقرمي‬ Actual Individual 8/12/2013 2,000 completed Planned Post Individual IC N/A 20-May-13 NA 28-May-13 NA NA NA N/A N/A N/A 01-Jul-13 Contracting consultant to design Revised Post 01-Jul-13 NA 15-Jul-13 NA 20-Jul-13 20-Aug-13 3 the M&E System Individual IC N/A NA NA N/A N/A N/A This activity has been absorved Actual 0 in the CRM system Planned Prior Firm CQS N/A 20-May-13 N/A 28-May-13 N/A N/A 16-Jun-13 28-Jun-13 N/A N/A 08-Jul-13 Contracting a firm for designing Revised Prior 10-Jul-13 N/A 24-Jul-13 N/A 29-Jul-13 12-Aug-13 N/A N/A 22-Aug-13 22-Sep-13 4 and developing Website Firm CQS N/A N/A on going / Actual Prior Firm CQS N/A 25-May-13 N/A 07-Jun-13 N/A N/A 26-Jun-13 3-Jul-13 N/A N/A 20-Jul-13 5,785 $ ‫برسبكتيÙ?‬ 8/20/2014 8,096 Variation Order in amount 2,889$ Planned Post Individual IC N/A 23-May-13 N/A 31-May-13 N/A N/A N/A N/A N/A N/A 07-Jun-13 Revised Post Individual IC N/A 15-Jul-13 N/A 29-Jul-13 N/A N/A N/A N/A N/A N/A 04-Aug-13 31-Aug-15 Recruitment of 11 Internship 5 Advisors (multicontract) Post IC N/A 8-Jun-13 N/A 9-Jul-13 N/A N/A N/A N/A N/A N/A 1-Sep-13 200,200 $ 11 singed contract For more details Actual Individual (multicontract) 8/31/2015 52,950 ongoing see Annex A Planned Post Individual IC N/A 23-May-13 N/A 31-May-13 N/A N/A N/A N/A N/A N/A 07-Jun-13 Revised Recruitment of 10 Business Post Individual IC N/A 10-Jul-13 N/A 24-Jul-13 N/A N/A N/A N/A N/A N/A 29-Jul-13 31-Aug-15 Development plan 6 dvisors(multicontract) 10 singed contract For more details Post Individual IC N/A 8-Jun-13 N/A 2-Jul-13 N/A N/A N/A N/A N/A N/A 22-Aug-13 246,000 $ Actual (multicontract) 8/30/2015 38,266 ongoing see Annex A Planned prior Firm SSS N/A N/A 20-Oct-13 27-Oct-13 N/A 27-Oct-13 02-Nov-13 20-Nov-13 N/A 25-Nov-13 01-Dec-13 Revised Selected institutes for internship prior Firm SSS N/A 05-Oct-13 10-Oct-13 24-Oct-13 N/A 24-Oct-13 29-Oct-13 12-Nov-13 N/A 30-Nov-13 05-Dec-13 05-Feb-14 7 training in Sana'a (first round) completed/ Actual prior Firm SSS N/A 20-Nov-14 20-Nov-14 20-Dec-14 N/A 20-Dec-14 22-Dec-14 29-Dec-14 N/A 28-Jan-14 30-Jan-14 24,450 $ ‫سييدز للتعليم‬ 3/3/2014 25,210 Variation Order in amount 760$ Planned prior Firm SSS N/A N/A 20-Oct-13 27-Oct-13 N/A 27-Oct-13 02-Nov-13 20-Nov-13 N/A 25-Nov-13 01-Dec-13 Revised Selected institutes for internship prior Firm SSS N/A 05-Oct-13 10-Oct-13 24-Oct-13 N/A 24-Oct-13 29-Oct-13 12-Nov-13 N/A 30-Nov-13 05-Dec-13 05-Feb-14 8 training in Aden (first round) Actual prior Firm SSS N/A 22-Dec-14 22-Dec-14 2-Jan-14 N/A 2-Jan-14 6-Jan-14 13-Jan-14 N/A 16-Feb-14 18-Feb-14 22,080 $ ‫مثابرون‬ 3/22/2014 22,080 completed Planned prior Firm SSS N/A N/A 26-Mar-14 05-Apr-14 N/A N/A 02-Apr-14 20-Apr-14 N/A 01-May-14 01-May-14 Revised Selected institutes for internship Prior Firm SSS N/A 05-Oct-14 10-Oct-14 24-Oct-14 N/A 24-Oct-14 29-Oct-14 12-Nov-14 N/A 30-Nov-14 05-Dec-14 05-Feb-15 9 training in Sana'a (Second round) Actual 0 Planned prior Firm SSS N/A N/A 26-Mar-14 05-Apr-14 N/A N/A 02-Apr-14 20-Apr-14 N/A 01-May-14 01-May-14 Selected institutes for internship 10 Revised prior Firm SSS N/A 05-Oct-14 10-Oct-14 24-Oct-14 N/A 24-Oct-14 29-Oct-14 12-Nov-14 N/A 30-Nov-14 05-Dec-14 05-Feb-15 training in Aden (Second round) Actual 0 Planned Post Individual IC N/A 18-May-13 N/A 10-May-13 N/A N/A N/A N/A N/A N/A 15-May-13 Revised Post Individual IC N/A 20-Jul-13 N/A 04-Aug-13 N/A N/A N/A N/A N/A N/A 09-Aug-13 31-Aug-15 11 Contracting Legal Consultant ‫عبدالكريم عبدالرحمن‬ Post IC N/A 29-Jun-13 N/A 2-Jul-13 N/A N/A N/A N/A N/A N/A 31-Jul-13 10,000 $ ‫عبداهلل الشيباني‬ Actual Individual 7/30/2015 2,500 ongoing Planned Post Individual IC N/A 26-May-13 N/A 15-May-13 N/A N/A N/A N/A N/A N/A 25-May-13 Revised Post Individual IC N/A 25-Jul-13 N/A 09-Aug-13 N/A N/A N/A N/A N/A N/A 14-Aug-13 05-Sep-13 12 Contracting Branding Consultant ‫رامي خالد ابراهيم‬ Post IC N/A 27-May-13 N/A 07-Jun-13 N/A N/A N/A N/A N/A N/A 15-Jun-13 2,500 $ ‫العبسي‬ Actual Individual 7/6/2013 2,500 completed Planned Prior Firm CQS N/A N/A 01-Jun-13 06-Jun-13 N/A N/A 01-Jul-13 08-Jul-13 N/A N/A 22-Jul-13 Extended till 31/05/2014 and Revised Prior Firm CQS N/A 01-Sep-13 06-Sep-13 20-Sep-13 N/A N/A 25-Sep-13 08-Oct-13 N/A N/A 18-Oct-13 13 Contracting Marketing Firm completed/ Actual Prior Firm CQS N/A 18-Jul-13 N/A 26-Jul-13 N/A N/A 24-Sep-13 29-Sep-13 N/A N/A 31-Oct-13 38,145 $ ‫سنونو‬ 2/15/2014 38,535 Variation Order in amount 390$ Planned post Individual IC N/A 01-Oct-13 N/A 15-Oct-13 N/A N/A N/A N/A N/A N/A 20-Oct-13 31-Aug-15 Contracting 6 Cluster Consultant 14 Revised (multicontract) post Individual IC N/A Mar14-Aug15 N/A Mar14-Aug15 N/A N/A N/A N/A N/A N/A Mar14-Aug15 Mar14-Aug15 Actual 0 Planned post Firm CQS N/A N/A 01-Jun-13 10-Jun-13 N/A N/A 15-Jun-13 01-Jul-13 N/A N/A 15-Jul-13 15 Revised Contracting Audit Consultancy post Firm CQS N/A 01-Jul-13 06-Jul-13 20-Jul-13 N/A N/A 25-Jul-13 09-Aug-13 N/A N/A 19-Aug-13 31-Aug-15 Actual post Firm CQS N/A 20-Jun-13 N/A 27-Jun-13 N/A N/A 2-Sep-13 15-Sep-13 N/A N/A 8-Oct-13 19,000 $ KPMG 12/31/2015 1,900 ongoing 16 Planned post Individual IC N/A Jun 13 - Jun 14 N/A N/A N/A N/A N/A N/A N/A N/A Jun 13 - Jun 15 31-Aug-15 Revised post Individual IC N/A Jun 13 -Aug 15 N/A N/A N/A N/A N/A N/A N/A N/A Jun 13 -Aug 15 Jun 13 -Aug 15 13 post IC N/A Aug13-May 14 N/A N/A N/A N/A N/A N/A N/A N/A Aug13-May 14 10,272 $ sep13-May 14 contracts /10 completed , 3 For more details Short term contracts (Develop (multicontract) see Annex B Actual Individual 6,102 ongoing ToR and specifications,evaluation Planned of Proposals/Offers,…etc ) post Individual IC N/A May 14-Aug 15 N/A N/A N/A N/A N/A N/A N/A N/A May 14-Aug 15 May 14-Aug 15 Revised This line has been added after the post Individual IC N/A May 14-Aug 15 N/A N/A N/A N/A N/A N/A N/A N/A May 14-Aug 15 904 $ May 14-Aug 15 approval of the TTL/ For more details Actual (multicontract) 0 1 ongoing contract see Annex D Planned post Individual IC N/A 15-Jul-13 N/A N/A N/A N/A N/A N/A N/A N/A 20-Jul-13 Contracting Consultant to design 31-Aug-15 17 Revised the ToR for selecting Market firm N/A N/A N/A N/A N/A N/A N/A N/A N/A Actual post Individual IC N/A 12-Jun-13 N/A 25-Jun-13 N/A N/A N/A N/A N/A N/A 26-Jun-13 560 $ ‫خالد محمد عبداهلل عامر‬ 7/4/2013 560 completed Procurement Plan for Goods/Works/Non-Consulting Services Updated 26/5/2014 ** Applicable in case of Bank's prior review Document (Date)** Bid Opening (Date) Contract Currency Bid Closing (Date) No Objection from Preparation of Bid Document (Date) Evaluation Report incurred to Date Contract Signed Contractor (incl. Objection to Bid Review by Bank Name, City, and Decision (Date) Contract (Date) Prequalification Contract Award Zip Code if US) Contract Value Award (Date)** Goods/ Works/ Reference No. Completion of Bid Invitation Evaluation of and Contract (Prior/ Post) Objection to Expenditure Application Country of Bank’s No Bank’s No Method of Selection Remarks Package/ Bank for Bidding SL No. (Date) (Date) NCS Description of Goods/ Works Planned prior Shopping N/A 20-Mar-13 27-Mar-13 06-Apr-13 20-Apr-13 20-Apr-13 24-Apr-13 29-Apr-13 01-May-13 Revised prior Shopping N/A 8/25/2013 9/9/2013 9/14/2013 9/28/2013 9/28/2013 10/9/2013 10/23/2013 10/28/2013 Extended till 01/05/2014 and 1 CRM System goods Completed, but still 10% of the contract Actual prior Shopping 21-Aug-13 28-Oct-13 10-Nov-13 20-Nov-13 04-Dec-13 09-Dec-13 amount did not paid for maintenance N/A 9/30/2013 12/6/2013 26,215 $ ‫Ù?وكاس سوÙ?ت نت يمن‬ 1/9/2014 23,593 issue Planned Post Shopping N/A 20-Mar-13 27-Mar-13 06-Apr-13 20-Apr-13 20-Apr-13 24-Apr-13 29-Apr-13 01-May-13 Revised Post Shopping N/A Jun13-Sep13 N/A Jun13-Sep13 Jun13-Sep13 Jun13-Sep13 Jun13-Sep13 N/A Jun13-Sep13 11 contract/ For more Actual Purchase orders details see Post Shopping N/A Jun13 -May 14 N/A Jun13 -May 14 Jun13 -May 14 Jun13 -May 14 Jun13 -May 14 N/A Jun13 -May 14 29,814 $ (multicontract) Jun13 -May 14 29,814 Completed Annex C 2 Computer & office equipment/goods goods The line 3 has Planned been added after the approval of the Post Shopping N/A May 14-Aug 15 N/A N/A N/A N/A N/A N/A May 14-Aug 15 (multicontract) TTL Revised Actual ‫‪Contract‬‬ ‫‪N.‬‬ ‫‪Name of Consultant‬‬ ‫‪Award Date‬‬ ‫‪Internship Advisors‬‬ ‫‪1‬‬ ‫محمد خالد محمد سالم‬ ‫‪9/1/2013‬‬ ‫‪2‬‬ ‫محمد أحمد محمد العقربي‬ ‫‪9/1/2013‬‬ ‫‪3‬‬ ‫سعيد محمد سعيد حميد‬ ‫‪9/1/2013‬‬ ‫‪4‬‬ ‫محمد أحمد صالح علي‬ ‫‪9/1/2013‬‬ ‫محمد قادري صالح محضار البان‬ ‫‪5‬‬ ‫‪9/1/2013‬‬ ‫‪6‬‬ ‫أسامة عبداللطيÙ? الÙ?سيل‬ ‫‪9/1/2013‬‬ ‫‪7‬‬ ‫نوال عبداهلل أحمد اإلرياني‬ ‫‪9/1/2013‬‬ ‫‪8‬‬ ‫سمير عبداهلل قاسم الحبيشي‬ ‫‪9/1/2013‬‬ ‫‪9‬‬ ‫لميس صالح عبداهلل الحبشي‬ ‫‪9/1/2013‬‬ ‫‪10‬‬ ‫راÙ?د أمين قاسم الصبري‬ ‫‪9/1/2013‬‬ ‫ميثاق عبدالرؤوÙ? أحمد الÙ?قية ‪11‬‬ ‫‪9/1/2013‬‬ ‫‪Note‬‬ ‫‪1- The consultants N. 4,9 Withdraw‬‬ ‫‪Business Development‬‬ ‫‪plan dvisors‬‬ ‫‪1‬‬ ‫محمد عمر محمد ناصر البان‬ ‫‪8/22/2013‬‬ ‫‪2‬‬ ‫وليد صالح موسى الحميري‬ ‫‪8/22/2013‬‬ ‫‪3‬‬ ‫أوسان عبدالقادر محمد سعيد‬ ‫‪8/22/2013‬‬ ‫‪4‬‬ ‫رضوان ياسين ابراهيم خان‬ ‫‪8/22/2013‬‬ ‫‪5‬‬ ‫معاذ هاشم صبري‬ ‫‪8/22/2013‬‬ ‫‪6‬‬ ‫ابراهيم هاشم يحي الشامي‬ ‫‪8/22/2013‬‬ ‫‪7‬‬ ‫لقاء عبداهلل محمد المستكا‬ ‫‪8/22/2013‬‬ ‫‪8‬‬ ‫معاذ سليم عبده قايد‬ ‫‪8/22/2013‬‬ ‫‪9‬‬ ‫انور مهيوب انعم‬ ‫‪8/22/2013‬‬ ‫‪10‬‬ ‫عبداهلل ناشر مرشد مقبل‬ ‫‪8/22/2013‬‬ ‫‪Note‬‬ ‫‪1- The consultants N. 7,9 Withdraw‬‬ ‫‪2- The contract N. 10 has been terminated‬‬ ‫‪3- The contracts below singed after some of the consultants withdraw‬‬ ‫‪1‬‬ ‫أروى جار اهلل صالح جوبح‬ ‫‪2/24/2014‬‬ ‫‪2‬‬ ‫أسامة عبداهلل أحمد الجوشعي‬ ‫‪5/6/2014‬‬ ‫‪3‬‬ ‫حسين عبداهلل صالح السري‬ ‫‪5/21/2014‬‬ Contract Completion Contract Value $ Date 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 18,200.00 8/31/2015 200,200.00 20,000.00 8/30/2015 20,000.00 8/31/2015 24,000.00 9/1/2015 20,000.00 9/1/2015 30,000.00 9/1/2015 26,000.00 9/1/2015 25,000.00 9/1/2015 27,000.00 9/1/2015 26,000.00 9/1/2015 28,000.00 9/1/2015 246,000.00 ultants withdraw 14,600.00 8/31/2015 23,000.00 8/31/2015 21,000.00 8/31/2015 ‫‪Contract‬‬ ‫‪Contract‬‬ ‫‪Contract‬‬ ‫‪Completion‬‬ ‫‪N.‬‬ ‫‪Name of Consultant‬‬ ‫‪Award Date Value $‬‬ ‫‪Date‬‬ ‫‪1‬‬ ‫اكرم جعÙ?ر احمد السقاÙ?‬ ‫‪8/22/2013‬‬ ‫‪728.00‬‬ ‫‪9/15/2013‬‬ ‫‪2‬‬ ‫ياسر محمد احمد العطاÙ?ي‬ ‫‪9/1/2013‬‬ ‫‪633.00‬‬ ‫‪9/30/2013‬‬ ‫‪3‬‬ ‫وثيق عبدالرؤوÙ? أحمد القدسي‬ ‫‪12/8/2013‬‬ ‫‪794.00‬‬ ‫‪12/21/2013‬‬ ‫‪4‬‬ ‫ياسر محمد احمد العطاÙ?ي‬ ‫‪12/8/2013‬‬ ‫‪383.00‬‬ ‫‪12/25/2013‬‬ ‫‪5‬‬ ‫وثيق عبدالرؤوÙ? أحمد القدسي‬ ‫‪1/8/2014‬‬ ‫‪564.00‬‬ ‫‪1/22/2014‬‬ ‫‪6‬‬ ‫ياسر محمد أحمد العطاÙ?ي‬ ‫‪2/25/2014‬‬ ‫‪210.00‬‬ ‫‪3/4/2014‬‬ ‫‪7‬‬ ‫يحي علي محمد االعوج‬ ‫‪12/25/2013‬‬ ‫‪600.00‬‬ ‫‪1/5/2014‬‬ ‫‪8‬‬ ‫عرÙ?ات رياض ناصر المرزوقي‬ ‫‪11/27/2013‬‬ ‫‪696.00‬‬ ‫‪12/23/2013‬‬ ‫‪9‬‬ ‫اكرم جعÙ?ر احمد السقاÙ?‬ ‫‪11/28/2013‬‬ ‫‪400.00‬‬ ‫‪12/12/2013‬‬ ‫‪10‬‬ ‫رامي خالد ابراهيم العبسي‬ ‫‪2/25/2014‬‬ ‫‪764.00‬‬ ‫‪3/17/2014‬‬ ‫‪11‬‬ ‫ياسر محمد أحمد العطاÙ?ي‬ ‫‪4/17/2014‬‬ ‫‪1,500.00‬‬ ‫‪7/17/2014‬‬ ‫‪12‬‬ ‫رامي حسين عوض عولقي‬ ‫‪4/20/2014‬‬ ‫‪1,500.00‬‬ ‫‪7/20/2014‬‬ ‫‪13‬‬ ‫عرÙ?ات رياض ناصر المرزوقي‬ ‫‪5/7/2014‬‬ ‫‪1,500.00‬‬ ‫‪7/7/2014‬‬ ‫‪10,272.00‬‬ ‫‪Contract‬‬ ‫‪Contract‬‬ ‫‪Award‬‬ ‫‪Completion‬‬ ‫‪N.‬‬ ‫‪Name of supplier‬‬ ‫‪Date‬‬ ‫‪Contract Value‬‬ ‫‪Date‬‬ ‫‪1‬‬ ‫حديث المدينة‬ ‫‪6/2/2013‬‬ ‫‪4,342‬‬ ‫‪6/5/2013‬‬ ‫‪2‬‬ ‫المازن لمستلزمات الكمبيوتر‬ ‫‪6/12/2013‬‬ ‫‪1,680‬‬ ‫‪NA‬‬ ‫‪3‬‬ ‫الصداقة للتجارة‬ ‫‪6/15/2013‬‬ ‫‪435‬‬ ‫‪NA‬‬ ‫‪4‬‬ ‫حديث المدينة‬ ‫‪6/15/2013‬‬ ‫‪1,170‬‬ ‫‪NA‬‬ ‫‪5‬‬ ‫شركة الحظا‬ ‫‪7/6/2013‬‬ ‫‪225‬‬ ‫‪NA‬‬ ‫‪6‬‬ ‫ريم سوÙ?ت‬ ‫‪7/7/2013‬‬ ‫‪1,847‬‬ ‫‪NA‬‬ ‫‪7‬‬ ‫مؤسسة عبدالواحد‬ ‫‪7/27/2013‬‬ ‫‪750‬‬ ‫‪NA‬‬ ‫‪8‬‬ ‫المركز الرقمي للحاسوب‬ ‫‪11/17/2013‬‬ ‫‪1,470‬‬ ‫‪NA‬‬ ‫‪9‬‬ ‫مؤسسة بن ثابت للتجارة‬ ‫‪11/17/2013‬‬ ‫‪450‬‬ ‫‪NA‬‬ ‫‪10‬‬ ‫اشتري أونالين‬ ‫‪2/20/2014‬‬ ‫‪16,875‬‬ ‫‪3/19/2014‬‬ ‫‪11‬‬ ‫بي سي يونايتد‬ ‫‪4/24/2014‬‬ ‫‪570‬‬ ‫‪NA‬‬ ‫‪29,814‬‬ Contract Contract Completion N. Name of Consultant Award Date Contract Value $ Date 1 ‫إدريس عبداهلل محمد حزام‬ 5/21/2014 904.00 6/15/2014