PROCUREMENT METHODS AND PRIOR REVIEW THRESHOLDS (a) Goods/Works: All ICB contracts for Goods and Works; First two NCB contracts for Goods and First two NCB contracts for Works irrespective of the cost of the First Shopping contract for Goods and First Shopping contract for Works. b) Consultants services FIRMS: All contracts with consulting firms estimated to cost US$300,000 or more; First contract with consulting firms selected on the basis of Consultants Qualifications (CQ) Individual Consultant All contracts with individual consultants estimated to US$50,000 or more All contracts with PIU staff irrespective of the cost of the contract ; General: - The Terms of Reference for all consultant contracts with consulting firms and individual consultants Short lists comprising entirely national consultants shall be for assignments below USD 300,000; Procurement method threshold ICB NCB $ USD $ USD Goods Works Goods Works ≥1.000.000 ≥ 5.000.000 < 1.000.000 <5.000.000 Prior review threshold ICB NCB $ USD $ USD Goods Works Goods Works All All First 2& >2.000.000;First 2&>10.000.000 AND PRIOR REVIEW THRESHOLDS or Works irrespective of the cost of the contract; ts Qualifications (CQ) sulting firms and individual consultants irrespective of their costs; ssignments below USD 300,000; method threshold SHOPPING $ USD Goods Works ≤ 100.000 ≤ 200.000 ew threshold CONSULTANTS $ USD Firms Individual* >1.000.000 > 300.000 *Individual Consultant Prior Review only under exceptional circumstances Plan vs./ Actual Days Execution Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval BEEP- Energy efficiency Proj ect Rev ie Proposal No Name of Cate Not Adv erti- Reception Short Technical No Final Ref No in Federation B&H October, w No Inv itation Submissi Obj ection Contract Comple- Assignment/Contract gory e # Selection sement of Listing Ev aluatio Obj ection Ev aluatio Start 2014 by Obj ection for RFP on Date to Signature tion Method for EOI expression and RFP n + PSC n Date Bank Date Date Date sign Date Date Date of interest ready Date Date Date Prior / contract Post A B D E F H I J Consulting firms COMPONENT 1 Combined Serv ices for Clinics and chosen Schools Detailed Energy Audit, P TME before, Design, Package 1: Audit of Design University Clinical Center A Sarajevo Ortopedic and Traumatology; BEEP- Surgery Clinic in Tuzla; Supervision, TME after, P143580-CQ- P CS CQ Prior 10/5/2015 14 24/5/2015 8 1/6/2015 7 8/6/2015 0 8/6/2015 10 18/6/2015 4 22/6/2015 0 22/6/2015 0 22/6/2015 7 29/6/2015 170 16/12/2015 0 16/12/2015 300 ######## Psychiatric Hospital Mostar Energy Labelling 02-CS-15-FBIH A 10/5/2015 14 24/5/2015 8 1/6/2015 7 8/6/2015 0 8/6/2015 10 18/6/2015 4 22/6/2015 0 22/6/2015 0 22/6/2015 7 29/6/2015 170 17/12/2015 0 1/2/2016 408 15/3/2017 Package 2 (10+3=13 obj ects) Ze-Do, Una-Sana, HNK Elementary School Ivana fra Frane Jukica Sivsa Usora; Elementary School 21. mart Doboj Jug; Gimnasium Rizah Odzeckic Zavidovici; Elementary School "Gazi Ferhad-beg" Combined Services BEEP- Tesanj; Secondary Mutual (Design, technical P143580-CQ- P CS CQ Prior 1/12/2015 14 15/12/2015 8 ######## 7 ######## 0 ######## 10 9/1/2016 4 13/1/2016 0 13/1/2016 0 13/1/2016 7 20/1/2016 2 22/1/2016 0 22/1/2016 450 16/4/2017 School Zepce; Hospital Bihać; monitoring (before and 04-CS-15-FBIH Elementary school Bosanska after), works supervision) Otoka; I Secondary school Dr. Husein Džanić & II secondary schoo l, Gymnasium; Elementary school Stijena Cazin; I & II Secondary school Cazin; Elementary School Fra Didaka Buntića Čitluk; Secondary 22.01.201 22.01.201 29.01.201 A 2/12/2015 13 15/12/2015 24 8/1/2016 10 05.02.2016. 0 05.02.2016. 0 05.02.2016. 12/2/2016 15/2/2016 15/2/2016 30/6/2018 6. 6. 6. Package 3 (12+4=16 obj ects Ze- Detailed Energy Audit, Do, Saraj ev o, HNK) TME before, Design P Secondary Mutual School completed for „Mula Stjepana Radica Usora; Mustafa Baseskija“ Elementary School Safvet-beg A Basagic Visoko; Elementary School Kulin Ban Visoko; Elementary School "Musa Cazim Catic" Zenica; Elementary School "Hamdija Kresevljakovic" Kakanj; Elementary School 15. April Kakanj; Elementary School „Mula Mustafa Baseskija“ Visoko; Combined Services BEEP- First elementary school (Design, technical P143580-CQ- CS CQ Prior 1/12/2015 14 15/12/2015 8 ######## 7 ######## 0 ######## 10 9/1/2016 4 13/1/2016 0 13/1/2016 0 13/1/2016 7 20/1/2016 2 22/1/2016 0 22/1/2016 450 16/4/2017 Zavidovici; Hospital Tesanj; monitoring (before and 05-CS-15-FBIH Elementary School „Zahid after), works supervision) Barucija; Elementary School „Hasim Spahic“; Elementary School „Srednje“ Ilijas; Secondary School Juraja Dalmatinca Mostar; Hospital Jablanica; Secondary School 22.01.201 22.01.201 29.01.201 A 2/12/2015 13 15/12/2015 08.01.2016. 05.02.2016. 0 05.02.2016. 0 05.02.2016. 12/2/2016 15/2/2016 15/2/2016 30/6/2018 6. 6. 6. BEEP- Package 2, 3 P143580-CQ- P (allocated) Audit of Design CS CQ Post 1/12/2015 14 15/12/2015 8 ######## 0 ######## 0 ######## 10 2/1/2016 0 2/1/2016 7 9/1/2016 0 9/1/2016 0 9/1/2016 2 11/1/2016 0 11/1/2016 65 16/3/2016 01-CS-15-FBIH A 2/12/2015 13 15/12/2015 14.01.2016. - 20.01.2016. 27.01.2016. 01.02.2016. 0 01.02.2016. 0 01.02.2016. 0 - 0 8/2/2016 15/2/2016 90 15/5/2016 Combined Services (Design for 18 objects, BEEP- Technical monitoring Package 4 (2017. buldings) P143580-CQ- P before and after for 19 CS CQ Post 15/1/2017 14 29/1/2017 2 31/1/2017 3 N/A 0 3/2/2017 7 10/2/2017 3 13/2/2017 0 N/A 2 15/2/2017 0 N/A 0 15/2/2017 0 15/2/2017 410 1/4/2018 (allocated) 06-CS-16-FBIH objects, Works Supervision for 13 Objects) A 17/1/2017 15 1/2/2017 15/2/2017 0 N/A 0 15/2/2017 7 22/2/2017 24/2/2017 0 N/A 0 24/2/2017 N/A 2/3/2017 0 2/3/2017 30/6/2019 Combined Services BEEP- (Works Supervision for 5 P143580-CQ- P federal level objects + 1 CS CQ Post 15/1/2017 14 29/1/2017 2 31/1/2017 3 N/A 0 3/2/2017 7 10/2/2017 3 13/2/2017 0 N/A 0 13/2/2017 2 N/A 2 15/2/2017 0 15/2/2017 410 1/4/2018 07-CS-16-FBIH Package 5 (2017. buildings) object for Piloting, Audit (allocated) of design for 19 objects) A 17/1/2017 15 1/2/2017 15/2/2017 0 N/A 0 15/2/2017 7 22/2/2017 24/2/2017 0 N/A 0 24/2/2017 N/A 6/3/2017 0 6/3/2017 30/6/2018 Combined Services BEEP- Package 6 (2018. buldings) (to (Design for 11 objects, P143580-CQ- P CS CQ Post 11/1/2018 14 25/1/2018 2 27/1/2018 3 N/A 0 30/1/2018 7 6/2/2018 3 9/2/2018 0 N/A 2 11/2/2018 0 N/A 0 11/2/2018 0 11/2/2018 450 7/5/2019 be allocated) Works Supervision for 11 08-CS-18-FBIH Objects) 03.01.2018 17.01.2018 A & 14 & 7 & 23/2/2018 0 N/A 0 27/2/2018 8 7/3/2018 8/3/2018 0 N/A 0 13/3/2018 N/A 26/3/2018 0 26/3/2018 525 31/8/2019 15.02.2018 22.02.2018 Combined Services BEEP- Package 7 (2019. buildings - 1 (Design for 1 object, P143580-CQ- P building in Konj ic /National CS CQ Post 20/5/2019 14 3/6/2019 2 5/6/2019 3 N/A 0 8/6/2019 7 15/6/2019 3 18/6/2019 0 N/A 0 18/6/2019 2 N/A 2 20/6/2019 0 20/6/2019 190 ######## Works Supervision for 1 10-CS-19-FBIH Monument) (to be allocated) Object) A Combined Services BEEP- Package 7 (2019. buildings - 2 (Design for 2 objects, P143580-CQ- P buildings in Saraj ev o and CS CQ Post 20/5/2019 14 3/6/2019 2 5/6/2019 3 N/A 0 8/6/2019 7 15/6/2019 3 18/6/2019 0 N/A 0 18/6/2019 2 N/A 2 20/6/2019 0 20/6/2019 190 ######## Works Supervision for 2 11-CS-19-FBIH Drv ar) (to be allocated) Objects) A Combined Services BEEP- Package 7 (2019. buildings - 4 (Design for 4 objects, P143580-CQ- P buildings in Mostar, Prozor, CS CQ Post 20/5/2019 14 3/6/2019 2 5/6/2019 3 N/A 0 8/6/2019 7 15/6/2019 3 18/6/2019 0 N/A 0 18/6/2019 2 N/A 2 20/6/2019 0 20/6/2019 190 ######## Works Supervision for 4 12-CS-19-FBIH Čitluk, Čaplj ina) (to be allocated) Objects) A Package 6 (2018. buldings - 11 BEEP- obj ects) P143580-CQ- P Audit of Design CS CQ Post 11/1/2018 14 25/1/2018 2 27/1/2018 3 N/A 0 30/1/2018 7 6/2/2018 3 9/2/2018 0 N/A 2 11/2/2018 0 N/A 0 11/2/2018 0 11/2/2018 50 2/4/2018 (to be allocated) 09-CS-18-FBIH A 3/1/2018 14 17/1/2018 23/2/2018 0 N/A 0 28/2/2018 8 8/3/2018 8/3/2018 0 N/A 0 13/3/2018 N/A 26/3/2018 0 26/3/2018 ######## Package 7 (2019. building - 1 BEEP- building in Konj ic /National P143580-CQ- P Monument) Audit of Design CS CQ Post 20/5/2019 14 3/6/2019 2 5/6/2019 3 N/A 0 8/6/2019 7 15/6/2019 3 18/6/2019 0 N/A 2 20/6/2019 0 N/A 0 20/6/2019 0 20/6/2019 30 20/7/2019 14-CS-19-FBIH (to be allocated) A Package 7 (2019. buildings - 6 BEEP- buildings) P143580-CQ- P Audit of Design CS CQ Post 20/5/2019 14 3/6/2019 2 5/6/2019 3 N/A 0 8/6/2019 7 15/6/2019 3 18/6/2019 0 N/A 2 20/6/2019 0 N/A 0 20/6/2019 0 20/6/2019 30 20/7/2019 (to be allocated) 15-CS-19-FBIH A Technical Design & BEEP- Package 7 (2019. buildings) Sepcification for AHC P143580-SSS- P (to be allocated) CS SSS Prior / 14 / 2 25/2/2019 3 28/2/2019 2 2/3/2019 7 9/3/2019 3 12/3/2019 0 N/A 2 14/3/2019 5 19/3/2019 0 19/3/2019 0 19/3/2019 30 18/4/2019 (two buildings: Mostar, 1-CS-19-FBIH Livno) A 8/2/2019 0 8/2/2019 41 21/3/2019 11 1/4/2019 14/5/2019 N/A 14/5/2019 F. Preliminary/Detailed energy audits BEEP- 72 detailed energy audits - Consultant engineering P143580-CQ- P CS CQ Post 1/2/2016 14 15/2/2016 8 23/2/2016 7 N/A 0 23/2/2016 10 4/3/2016 4 8/3/2016 0 N/A 0 8/3/2016 7 N/A 2 10/3/2016 0 10/3/2016 90 8/6/2016 2017. buldings service 11-CS-16-FBIH A 19/4/2016 14 4/5/2016 6/5/2016 N/A 9/5/2016 7 16/5/2016 19/5/2016 0 N/A 0 24/5/2016 0 N/A 0 9/6/2016 0 9/6/2016 90 7/9/2016 BEEP- 30 detailed energy audits - Consultant engineering P143580-CQ- P CS CQ Post 25/5/2016 14 8/6/2016 8 16/6/2016 7 N/A 0 16/6/2016 10 26/6/2016 4 30/6/2016 0 N/A 0 30/6/2016 7 N/A 2 2/7/2016 0 2/7/2016 45 16/8/2016 2017. buldings service 18-CS-16-FBIH A 4/7/2016 14 18/7/2016 25/7/2016 N/A 3/8/2016 7 10/8/2016 1 11/8/2016 0 N/A 0 12/8/2016 0 N/A 0 25/8/2016 25/8/2016 60 ######## G. Social monitoring and ev aluation BEEP- Social monitoring and P143580-CQ- P Consultant services CS CQ Post 20/12/2015 14 3/1/2016 8 11/1/2016 7 N/A 0 11/1/2016 10 21/1/2016 4 25/1/2016 0 N/A 0 25/1/2016 7 N/A 2 27/1/2016 0 27/1/2016 790 27/3/2018 evaluation -(IA) (alocated) 12-CS-15-FBIH A 11.01.2016. 25.01.2016. 1/2/2016 - 9/2/2016 7 16/2/2016 1 17/2/2016 0 N/A 0 28/3/2016 - 5/4/2016 0 5/4/2016 4/10/2019 TOTAL COMPONENT 1 COMPONENT 2 Sub-Component A: Support for scalable financing mechanisms Consultant firms BEEP- P143580-IC- P Senior International Energy Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Efficiency Consultant for the I Development of the Issue and A Options Study on Scalable 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 11/8/2017 31/8/2017 48 30/4/2018 Financing Mechanisms BEEP- IC 30/4/2019 10 10/5/2019 7 17/5/2019 6 23/5/2019 0 23/5/2019 8 1/6/2019 1/6/2019 183 1/12/2019 P143580-IC- 13-CS-19-FBIH- BEEP- P143580-IC- Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Financial Expert for the II Development of the Issue and A Options Study on Scalable 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 50 30/4/2018 Financing Mechanisms 10/8/2019 BEEP- SS 11/2/2019 11/2/2019 180 P143580-IC- 13-CS-19-FBIH- 10/2/2017 BEEP- P143580-IC- Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 13-CS-16-FBIH- Policy/Regulatory Expert for the III Development of the Issue and Options Study on Scalable A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 65 30/4/2018 Financing Mechanisms BEEP- IC 20/7/2019 3 23/7/2019 0 23/7/2019 7 30/7/2019 3 2/8/2019 2/8/2019 7 9/8/2019 10/8/2019 113 1/12/2019 P143580-IC- 13-CS-19-FBIH- BEEP- Technical Expert for the P143580-IC- Development of the Issue and Consultant service CS IC Post 15/12/2016 14 29/12/2016 8 6/1/2017 7 13/1/2017 0 13/1/2017 10 23/1/2017 4 27/1/2017 0 27/1/2017 0 27/1/2017 7 3/2/2017 2 10/2/2017 0 10/2/2017 10/2/2017 13-CS-16-FBIH- Options Study on Scalable IV Financing Mechanisms A 20/2/2017 14 6/3/2017 8 14/3/2017 7 21/3/2017 0 21/3/2017 10 31/3/2017 4 4/4/2017 0 4/4/2017 0 4/4/2017 7 11/4/2017 2 22/8/2017 31/8/2017 40 30/4/2018 Sub-Component B: Capacity building BEEP- Training Municipality energy P143580-CQ- P Consultant service CS CQ Post 1/12/2016 14 15/12/2016 8 ######## 7 ######## 0 ######## 10 9/1/2017 4 13/1/2017 0 13/1/2017 0 13/1/2017 7 20/1/2017 2 27/1/2017 0 27/1/2017 450 22/4/2018 management-certification 14-CS-16-FBIH A 4/1/2017 14 18/1/2017 27/1/2017 0 27/1/2017 0 30/1/2017 7 6/2/2017 1 7/2/2017 0 7/2/2017 0 7/2/2017 0 7/2/2017 0 2/3/2017 2/3/2017 30/9/2019 BEEP- "Communications, awareness P143580-CQ- P Consultant service CS multi CQ Post 15/1/2016 14 29/1/2016 8 6/2/2016 7 13/2/2016 0 13/2/2016 10 23/2/2016 4 27/2/2016 0 27/2/2016 0 27/2/2016 7 5/3/2016 2 12/3/2016 0 12/3/2016 811 1/6/2018 raising and outreach". 15-CS-16-FBIH A 13.01.2016. 26.01.2016. 1/2/2016 - 9/2/2016 7 16/2/2016 17/2/2016 - 19/2/2016 - 22/2/2016 22/2/2016 30/6/2018 BEEP- P143580-CQ- P Promotion of EE results Consultant service CS multi CQ Post 20/2/2016 14 5/3/2016 8 13/3/2016 7 20/3/2016 0 20/3/2016 10 30/3/2016 4 3/4/2016 0 3/4/2016 0 3/4/2016 7 10/4/2016 2 17/4/2016 0 17/4/2016 775 1/6/2018 16-CS-16-FBIH A 22/2/2016 14 7/3/2016 20/3/2016 - 20/3/2016 24/3/2016 25/3/2016 - 29/3/2016 0 - 0 5/4/2016 5/4/2016 30/6/2018 Developing and implementing a BEEP- communication campaign and P143580-CQ- P promotion activties for the energy Consultant service CS multi SS Post 8/8/2018 7 15/8/2018 6 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 27/8/2018 0 27/8/2018 0 29/8/2018 0 29/8/2018 ######## 16-CS-18-FBIH efficiency improvements in public buildings A 8/8/2018 7 15/8/2018 6 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 21/8/2018 0 27/8/2018 0 27/8/2018 0 3/9/2018 0 3/9/2018 ######## TOTAL COMPONENT 2 COMPONENT 3 Proj ect management BEEP- P143580-IC- 01-CS-14- Project Coordinator Consultant service CS IC Prior 21/2/2014 7 28/2/2014 3/3/2014 12/3/2014 1 13/3/2014 1 14/3/2014 0 14/3/2014 0 12/3/2014 0 17/3/2014 ######## 16/12/2015 0 16/12/2015 167 31/5/2016 FBIH/BEEP- P143580-IC- 001-FBIH IC Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 2/7/2018 ######## BEEP- P143580-IC- 02-CS-14- Procurement specialist Consultant service CS IC Prior 21/2/2014 7 28/2/2014 3/3/2014 12/3/2014 1 13/3/2014 1 14/3/2014 0 14/3/2014 0 12/3/2014 0 17/3/2014 ######## 16/12/2015 0 16/12/2015 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 21/7/2018 9 30/7/2018 2/8/2018 2/8/2018 6/8/2018 0 6/8/2018 ######## BEEP- P143580-IC- 06-CS-14- Financial specialist Consultant service CS IC Prior 26/8/2015 18 13/9/2015 ######## ######## 1 ######## 7 ######## 1 ######## 3 ######## 1 ######## 7/1/2016 16/12/2015 0 16/12/2015 167 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 328 25/4/2017 Prior 21/4/2017 21/4/2017 1 22/4/2017 1 23/4/2017 0 26/4/2017 0 9/5/2017 0 9/5/2017 9/5/2017 11/5/2017 0 11/5/2017 ######## 11/5/2017 11/5/2017 ######## BEEP- P143580-IC- 04-CS-14- Technical Expert I Consultant service CS multi IC Prior 22/10/2014 14 5/11/2014 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 16/12/2015 167 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 0 1/6/2016 ######## BEEP- P143580-IC- Technical Expert II Consultant service CS multi IC Prior 22/10/2014 14 5/11/2014 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 16/12/2015 167 31/5/2016 05-CS-14- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 30/6/2018 2/7/2018 ######## BEEP- P143580-IC- 03-CS-14- Administrative assistant Consultant service CS IC Prior 22/10/2014 14 5/11/2014 7 ######## 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 26/1/2015 ######## 16/12/2015 0 16/12/2015 167 31/5/2016 FBIH/BEEP- P143580-IC- Post 1/6/2016 0 1/6/2016 ######## 1/6/2016 0 1/6/2016 ######## BEEP- P143580-IC- Temporary Technical Expert Consultant service CS IC Post 10/8/2016 5 15/8/2016 16/8/2016 N/A N/A N/A N/A N/A 16/8/2016 N/A 23/8/2016 23/8/2016 ######## 44-CS-16-FBIH IC Post 20/2/2018 7 27/2/2018 27/2/2018 N/A N/A N/A N/A N/A 27/2/2018 N/A 28/2/2018 1/3/2018 121 30/6/2018 IC Post 21/7/2018 9 30/7/2018 0 1/8/2018 ######## 21/7/2018 9 30/7/2018 2/8/2018 2/8/2018 9/8/2018 1/10/2018 30/6/2019 BEEP- Financial Software for World P143580-SSS- P software SSS Prior 14/9/2015 7 21/9/2015 7 28/9/2015 7 5/10/2015 7 ######## 7 ######## 3 ######## 1 ######## 1 ######## 5 ######## 48 15/12/2015 0 16/12/2015 30 15/1/2016 Bank Project 28-S-15-FBIH A 14/10/2015 0 14/10/2015 0 ######## 0 ######## 0 ######## 1 ######## 11 ######## 0 ######## 0 ######## 0 ######## 51 16/12/2015 16/12/2015 30 15/1/2016 Incremental operating costs A Annual financial audit A 1/9/2014 1398 30/6/2018 TOTAL COMPONENT 3 contarct Siganture Plan vs./ Actual Days Execution Days Execution Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Days Interval Review Subm is- No Invita- Bid- Evalu- No Contract Com ple- date BEEP- Energy efficiency Project in Nam e of Cate Selection by Bank sion/ Start Ref no Note # Objection tion Opening ation & Objection Aw ard tion Federation B&H Decem ber, 2013 Assignm ent/Contract gory Method Prior / Readiness Date Date Date Date Recom m . Date + PSC Date Date Post Date CLINICS BEEP-P143580- PACKAGE 1 University Clinical Center Works on reconstruction NCB-29-W-15- W NCB Prior 1/5/2015 7 8/5/2015 3 11/5/2015 28 8/6/2015 14 22/6/2015 4 26/6/2015 5 1/7/2015 16 17/7/2015 0 17/7/2015 123 17/11/2015 1 Sarajevo Ortopedic and Traumatology of Clinics FBIH A 29.04.2015. 03.05.2015. 13.05.2015. 09.06.2015. 30.06.2015. 08.07.2015. 18.12.2015. 18.12.2015. 02.03.2016. 30.06.2016. PACKAGE 2 LOT 1 - Psychiatric Hospital W 20/5/2015 7 27/5/2015 2 29/5/2015 28 26/6/2015 14 10/7/2015 7 17/7/2015 3 20/7/2015 11 31/7/2015 0 31/7/2015 114 22/11/2015 1 BEEP-P143580- Mostar Works on reconstruction NCB- 30-W-15- NCB Prior of Clinics FBIH PACKAGE 2 LOT 2 - Health Centre Tuzla - W 20/5/2015 7 27/5/2015 2 29/5/2015 28 26/6/2015 14 10/7/2015 7 17/7/2015 3 20/7/2015 11 31/7/2015 0 31/7/2015 121 29/11/2015 1 Surgery Clinic A 14.05.2015. 18.05.2015. 21/5/2015 17.06.2015. 08.08.2015. 22.09.2015. 18.12.2015. 18.12.2015. 01.02.2016. 31.05.2016. CANTONS 2016. buildings BEEP-P143580- PACKAGE 3 - 2016. buildings (3 Works on reconstruction NCB-31-W-16- P W NCB Post 18/4/2016 0 18/4/2016 0 18/4/2016 21 9/5/2016 5 14/5/2016 5 19/5/2016 2 21/5/2016 30 20/6/2016 0 20/6/2016 90 18/9/2016 1 buildings) (allocated) of Sarajevo Canton FBIH A 20/4/2016 21 12/5/2016 15/7/2016 N/A 15/7/2016 22/7/2016 1/8/2016 90 30/10/2016 BEEP-P143580- PACKAGE 5 - 2016. buildings (5 Works on reconstruction NCB-33-W-16- P W NCB Post 18/4/2016 0 18/4/2016 0 18/4/2016 21 9/5/2016 5 14/5/2016 5 19/5/2016 2 21/5/2016 30 20/6/2016 0 20/6/2016 90 18/9/2016 1 buildings) (allocated) of ZE-DO Canton FBIH A 29/4/2016 21 20/5/2016 13/7/2016 N/A 13/7/2016 22/7/2016 8/8/2016 114 30/11/2016 PACKAGE 6 - LOT 1 - 2016. buildings P W NCB Post 25/4/2016 0 25/4/2016 0 25/4/2016 21 16/5/2016 5 21/5/2016 5 26/5/2016 2 28/5/2016 30 27/6/2016 0 27/6/2016 90 25/9/2016 1 (2 buildings) (allocated) BEEP-P143580- Works on reconstruction NCB-34-W-16- of HNK Canton FBIH PACKAGE 6 - LOT 2 - 2016. buildings W NCB Post 25/4/2016 0 25/4/2016 0 25/4/2016 21 16/5/2016 5 21/5/2016 5 26/5/2016 2 28/5/2016 30 27/6/2016 0 27/6/2016 90 25/9/2016 1 (5 buildings) (allocated) A LOT 1 27/5/2016 21 17/6/2016 14/7/2016 N/A 14/7/2016 25/7/2016 3/8/2016 139 20/12/2016 LOT 2 27/5/2016 21 17/6/2016 14/7/2016 N/A 14/7/2016 25/7/2016 8/8/2016 145 31/12/2016 CANTONS 2017. buildings BEEP-P143580- Works on reconstruction PACKAGE 7 2017. buildings (4 NCB-35-W-16- P of 4 objects in HNK W NCB Post 1/7/2017 0 1/7/2017 0 1/7/2017 21 22/7/2017 5 27/7/2017 14 10/8/2017 2 12/8/2017 30 11/9/2017 0 11/9/2017 120 9/1/2018 1 buildings) (allocated) FBIH Canton A 16/11/2017 7/12/2017 20/12/2017 20/12/2017 21/12/2017 9/1/2018 1/2/2018 180 31/7/2018 BEEP-P143580- Works on reconstruction PACKAGE 8 2017. buildings (5 buildings) NCB-36-W-16- P of 5 objects in ZE-DO W NCB Post 3/5/2017 0 3/5/2017 0 3/5/2017 21 24/5/2017 5 29/5/2017 14 12/6/2017 2 14/6/2017 30 14/7/2017 0 14/7/2017 120 11/11/2017 1 (allocated) FBIH Canton A 15/5/2017 21 5/6/2017 10/7/2017 10/7/2017 28/7/2017 22/8/2017 23/8/2017 240 20/4/2018 Works on reconstruction BEEP-P143580- PACKAGE 9 2017. buildings (6 buildings) of 1 object in Canton NCB-37-W-16- P W NCB Post 15/6/2017 0 15/6/2017 0 15/6/2017 21 6/7/2017 5 11/7/2017 14 25/7/2017 2 27/7/2017 30 26/8/2017 0 26/8/2017 120 24/12/2017 1 (allocated) Sarajevo & 5 federal level FBIH objects A 7/6/2017 21 28/6/2017 17/7/2017 17/7/2017 28/7/2017 22/8/2017 23/8/2017 162 1/2/2018 BEEP-P143580- Works on reconstruction PACKAGE 10 2017. buildings (2 buildings) NCB-38-W-16- P of 2 objects in Livanjski W NCB Post 3/5/2017 0 3/5/2017 0 3/5/2017 21 24/5/2017 5 29/5/2017 14 12/6/2017 2 14/6/2017 30 14/7/2017 0 14/7/2017 120 11/11/2017 1 (allocated) FBIH Canton A 22/5/2017 21 12/6/2017 10/7/2017 10/7/2017 28/7/2017 22/8/2017 23/8/2017 250 30/4/2018 BEEP-P143580- Works on reconstruction PACKAGE 11 2017. buildings (1 building) NCB-44-W-16- P of 1 object in Canton W NCB Post 15/7/2017 0 15/7/2017 0 15/7/2017 21 5/8/2017 5 10/8/2017 14 24/8/2017 2 26/8/2017 30 25/9/2017 0 25/9/2017 120 23/1/2018 1 (allocated) FBIH Sarajevo A 17/8/2017 21 7/9/2017 18/9/2017 18/9/2017 19/9/2017 4/10/2017 16/10/2017 242 15/6/2018 BEEP-P143580- Works on reconstruction PACKAGE 12 2017. buildings (1 building) NCB-45-W-16- of 1 object in ZE-DO W NCB Post 27/6/2017 0 27/6/2017 0 27/6/2017 21 18/7/2017 5 23/7/2017 14 6/8/2017 2 8/8/2017 30 7/9/2017 0 7/9/2017 90 6/12/2017 (allocated) FBIH Canton A 11/7/2017 21 1/8/2017 17/8/2017 17/8/2017 21/8/2017 12/9/2017 13/9/2017 90 12/12/2017 CANTONS 2018. buildings BEEP-P143580- Works on reconstruction PACKAGE 13 2018. buildings (3 NCB-46-W-18- P of 3 objects in HNK W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 buildings) (allocated) FBIH Canton A 13/8/2018 22 4/9/2018 14/9/2018 14/9/2018 20/9/2018 21/9/2018 8/10/2018 221 17/5/2019 BEEP-P143580- Works on reconstruction PACKAGE 14 2018. buildings (5 buildings) NCB-47-W-18- P of 5 objects in ZE-DO W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 (allocated) FBIH Canton A 14/8/2018 22 5/9/2018 13/11/2018 13/11/2018 23/11/2018 23/11/2018 12/17/2018 154 20/5/2019 BEEP-P143580- Works on reconstruction PACKAGE 15 2018. buildings (6 buildings) NCB-48-W-18- P of 3 object in Canton W NCB Post 15/6/2018 0 15/6/2018 0 15/6/2018 21 6/7/2018 5 11/7/2018 14 25/7/2018 2 27/7/2018 30 26/8/2018 0 26/8/2018 120 24/12/2018 1 (allocated) FBIH Sarajevo A 4/9/2018 20 24/9/2018 22/10/2018 22/10/2018 24/10/2018 29/10/2018 26/11/2018 182 27/5/2019 CANTONS 2019. buildings BEEP-P143580- PACKAGE 16 2019. buildings (allocated) - Works on reconstruction NCB-49-W-19- W NCB Post 1/8/2019 0 1/8/2019 0 1/8/2019 21 22/8/2019 5 27/8/2019 10 6/9/2019 2 8/9/2019 20 28/9/2019 0 28/9/2019 90 27/12/2019 1 building: Konjic /National Monument of xxx objects in 2019. FBIH A BEEP-P143580- PACKAGE 16 2019. buildings (allocated) - Works on reconstruction NCB-50-W-19- W NCB Post 1/8/2019 0 1/8/2019 0 1/8/2019 21 22/8/2019 5 27/8/2019 10 6/9/2019 2 8/9/2019 20 28/9/2019 0 28/9/2019 90 27/12/2019 3 buildings: Čapljina, Čitluk, Drvar of xxx objects in 2019. FBIH A BEEP-P143580- PACKAGE 16 2019. buildings (allocated) - Works on reconstruction NCB-51-W-19- W NCB Post 1/8/2019 0 1/8/2019 0 1/8/2019 21 22/8/2019 5 27/8/2019 10 6/9/2019 2 8/9/2019 20 28/9/2019 0 28/9/2019 90 27/12/2019 2 buildings: Mostar, Prozor of xxx objects in 2019. FBIH A BEEP-P143580- PACKAGE 16 2019. buildings (allocated) - Works on reconstruction NCB-52-W-19- W NCB Post 1/8/2019 0 1/8/2019 0 1/8/2019 21 22/8/2019 5 27/8/2019 10 6/9/2019 2 8/9/2019 30 8/10/2019 0 8/10/2019 90 6/1/2020 1 buildins: Sarajevo of xxx objects in 2019. FBIH A BEEP-P143580- JU “Druga osnovna škola� Zavidovići Works on replacement of NCB-53-W-19- W NCB Post 20/7/2019 5 25/7/2019 21 15/8/2019 5 20/8/2019 10 30/8/2019 10 9/9/2019 14 23/9/2019 60 22/11/2019 (Primary school in Zavidovići) roof FBIH A Total w orks - Com ponent 1 / Hospitals, Schools and Adm inistrative buildings/ GOODS Purchasing and Instalation (Performance Monitoring System for measuring the BEEP-P143580-SH- temperature and humidity) (20+7=27 G SH Post 5/2/2016 2 7/2/2016 3 10/2/2016 14 24/2/2016 1 25/2/2016 3 28/2/2016 0 28/2/2016 0 28/2/2016 0 28/2/2016 20 19/3/2016 1 39-G-16-FBIH buildings) - 2016./2017. buldings (allocated) A 25.01.2016. 01.02.2016. 3/2/2016 3/2/2016 - 5/2/2016 8/2/2016 8/2/2016 105 23/5/2016 Purchasing and Instalation (Performance Monitoring System for measuring the heat BEEP-P143580-SH- energy usage) (20+7=27 buildings) - G SH Post 5/2/2016 2 7/2/2016 3 10/2/2016 14 24/2/2016 1 25/2/2016 3 28/2/2016 0 28/2/2016 0 28/2/2016 0 28/2/2016 20 19/3/2016 1 40-G-16-FBIH 2016./2017. buldings (allocated) A 25.01.2016. 01.02.2016. 3/2/2016 3/2/2016 - 5/2/2016 8/2/2016 8/2/2016 105 23/5/2016 Purchasing and Instalation (Performance Monitoring System for measuring the BEEP-P143580-SH- temperature and humidity) (for 19 G SH Post 15/1/2017 0 15/1/2017 0 15/1/2017 7 22/1/2017 1 23/1/2017 3 26/1/2017 0 26/1/2017 0 26/1/2017 0 26/1/2017 30 25/2/2017 1 41-G-16-FBIH buildings) - 2017. buldings (allocated) A 23/1/2017 0 23/1/2017 0 23/1/2017 7 30/1/2017 2 1/2/2017 0 1/2/2017 0 1/2/2017 0 16/2/2017 0 16/2/2017 30 18/3/2017 1 Purchasing and Instalation (Performance Monitoring System for measuring the heat BEEP-P143580-SH- energy usage) (for 19 buildings) - 2017. G SH Post 15/1/2017 0 15/1/2017 0 15/1/2017 7 22/1/2017 1 23/1/2017 3 26/1/2017 0 26/1/2017 0 26/1/2017 0 26/1/2017 30 25/2/2017 1 42-G-16-FBIH buldings (allocated) A 23/1/2017 0 23/1/2017 0 23/1/2017 7 30/1/2017 2 1/2/2017 0 1/2/2017 0 1/2/2017 0 16/2/2017 0 16/2/2017 30 18/3/2017 1 BEEP-P143580-SH- Purchasing of Motor Vechicle G SH Post 10/2/2016 8 18/2/2016 3 22/2/2016 14 22/2/2016 1 22/2/2016 3 - 0 7/3/2016 0 8/3/2016 0 8/3/2016 30 7/4/2016 1 43-G-16-FBIH (allocated) A 10/2/2016 8 18/2/2016 3 22/2/2016 14 22/2/2016 1 22/2/2016 3 - 0 7/3/2016 0 8/3/2016 0 8/3/2016 30 7/4/2016 1 Procure and install additional equipment of seasonal pellet tank w ith pellet transporter BEEP-P143580-SH- from pellet tank to pellet boiler to make it G SH Post 11/9/2017 0 11/9/2017 0 11/9/2017 14 25/9/2017 1 26/9/2017 3 29/9/2017 0 29/9/2017 0 29/9/2017 0 29/9/2017 20 19/10/2017 1 44-G-17-FBIH easier for beneficiaries for 7 public buildings (allocated) A 11/9/2017 0 11/9/2017 0 11/9/2017 7 18/9/2017 7 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 130 2/2/2018 Procure and install automatic regulation system for 11 objects as follow s: a. Comprehensive automatic regulation system for 5 objects; BEEP-P143580-SH- b. Room temperature sensors w ith G SH Post 11/9/2017 0 11/9/2017 0 11/9/2017 14 25/9/2017 1 26/9/2017 3 29/9/2017 0 29/9/2017 0 29/9/2017 0 29/9/2017 20 19/10/2017 1 45-G-17-FBIH programming of existing controller w ith goal to make correction in line w ith interior temperature for 6 objects. A 11/9/2017 0 11/9/2017 0 11/9/2017 7 18/9/2017 7 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 0 25/9/2017 202 15/4/2018 BEEP-P143580-SH- Purchasing and Instalation of required G SH Post 30/1/2018 0 30/1/2018 0 30/1/2018 14 13/2/2018 1 14/2/2018 3 17/2/2018 0 17/2/2018 0 17/2/2018 0 17/2/2018 30 19/3/2018 1 46-G-19-FBIH goods (TRW & Automatisation) A Purchasing and Instalation of upgrade of BEEP-P143580-SH- the existing Web registry of Energy G DC Prior 9/5/2019 6 15/5/2019 1 16/5/2019 8 24/5/2019 3 29.05.20419 6 4/6/2019 1 5/6/2019 3 8/6/2019 0 8/6/2019 120 6/10/2019 1 47-G-19-FBIH Building Certificates softw are at the Ministry w ith New Modules A Purchasing and Instalation of an BEEP-P143580-SH- Automated data readout system from G SH Post 5/8/2019 2 7/8/2019 2 9/8/2019 14 23/8/2019 3 26/8/2019 0 26/8/2019 1 27/8/2019 1 28/8/2019 0 28/8/2019 40 7/10/2019 48-G-19-FBIH installed meters of heat energy consumption (35 objects) A 1