Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) EAST ASIA AND PACIFIC | Philippines | Social, Urban, Rural and Resilience Global Practice Global Practice | Recipient Executed Activities | Specific Investment Loan | FY 2006 | Seq No: 12 | ARCHIVED on 19-Aug-2016 | ISR24631 | Implementing Agencies: Bangsamoro Development Agency Key Dates Key Project Dates Bank Approval Date:20-Jul-2005 Effectiveness Date:30-Mar-2006 Planned Mid Term Review Date:15-May-2009 Actual Mid-Term Review Date:15-May-2009 Original Closing Date:31-Dec-2015 Revised Closing Date:31-Dec-2016 Project Development Objectives Project Development Objective (from Project Appraisal Document) Project Development Objective Communities of conflict-affected areas, internally displaced people, and rebel returnees benefitfromvisible restoration of some basic services of their choice and sustained by more accountable Local Government Units (LGUs). Has the Project Development Objective been changed since Board Approval of the Project Objective? Yes Board Approved Revised Project Development Objective (If project is formally restructured)PHRPDODEL To improve social and economic recovery in targeted conflict-affected communities of Mindanao through activities which promote confidence- building, peace and demand-driven governance. Components Name BLOCK GRANTS:(Cost $14.12 M) CAPACITY-BUILDING:(Cost $13.01 M) IMPLEMENTATION SUPPORT AND TRAINING:(Cost $1.24 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  High  High 8/19/2016 Page 1 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) Implementation Status and Key Decisions The project is making steady progress towards achieving the project development objective. Half a million people (51% of whom are women) in 225 villages have benefitted from 379 completed subprojects such as water systems, access roads, post-harvest facilities and farming/fishing equipment. These subprojects have reduced travel time to market, increased agricultural productivity, reduced post-harvest costs and increased access to basic services such as clean water. An additional 169 subprojects are currently under preparation that will provide clean water, access roads, farming equipment and other basic services to needy communities in 91 conflict-affected villages across Mindanao by the end of 2016. Functional literacy courses will also be offered to people who were unable to complete schooling. At its core, the project seeks to build the capacity of the Bangsamoro Development Agency (BDA), the development arm of the Moro Islamic Liberation Front (MILF). The MILF signed the Comprehensive Agreement on the Bangsamoro (CAB) with the Government of the Philippines in 2014, ending seventeen years of peace talks. The centerpiece of the agreement is the establishment of a new autonomous political entity – known as the Bangsamoro – to replace the existing Autonomous Region in Muslim Mindanao. The Mindanao Trust Fund has been working to prepare MILF officials, including from the BDA, for future roles in government by equipping them with the skills and knowledge necessary to plan and manage development resources. Capacity-building efforts are moving in a positive direction. The BDA has expanded from a small group of volunteers to an agency with eight offices and over 300 staff. In 2016 it has issued new Agency administrative and financial policies and manuals, strengthening core systems. It is also demonstrating increased capacity by delivering a large number of subprojects across a highly geographically disbursed region. The program is also making solid progress on social cohesion and confidence-building objectives. In 2016 the program has evolved to directly support implementation of the Comprehensive Agreement on the Bangsamoro by extending assistance to communities in the Six Acknowledged Camps of the MILF. Transforming these areas into peaceful and productive communities is identified in the CAB as a critical confidence-building measure. The program’s community based approach not only builds close working relations between the MILF and government – once adversaries but now partners in peace – but also generates social cohesion on the ground by bringing together diverse communities of Muslims, Christians and Indigenous Peoples. 8/19/2016 Page 2 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) 8/19/2016 Page 3 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Moderate  Moderate Macroeconomic  --  Low  Low Sector Strategies and Policies  --  High  High Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Substantial  Substantial Fiduciary  --  Substantial  Substantial Environment and Social  --  Low  Low Stakeholders  --  Substantial  Substantial Other  --  Substantial  Substantial Overall  --  High  High Results Project Development Objective Indicators PHINDPDOTBL  Communities report better access to basic services (time, distance and cost) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Jan-2006 30-Apr-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. 8/19/2016 Page 4 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDPDOTBL  Percentage of beneficiaries who receive entrepreneurship training and support who establish a new enterprise (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 22.00 77.00 50.00 Date 11-Dec-2012 29-Dec-2015 09-Aug-2016 31-Oct-2016 PHINDPDOTBL  Increase in number of community members reporting trust in other members/groups within their community (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. PHINDPDOTBL  Increase in number of community members who think their opinion counts in what needs to be done in their community (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Jul-2012 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. 8/19/2016 Page 5 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDPDOTBL  Increase in number of community members confident that the BDA/MILF and the government of the Philippines can work together for the benefit of the community (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Jul-2012 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. PHINDPDOTBL  The economic internal rate of return for community sub-projects will be at or beyond 12%. (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.90 12.90 12.00 Date 03-Apr-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments The current figure is based on a sample of projects from the 2012 independent assessment. This exercise will be repeated for the 2016/2017 indepednet assessment. PHINDPDOTBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 497488.00 497488.00 550000.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments The beneficiary numbers will increase once the current set of subprojects commences implementation. PHINDPDOTBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target 8/19/2016 Page 6 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) Value 0.00 252424.00 252424.00 275000.00 Overall Comments Intermediate Results Indicators PHINDIRITBL  Beneficiaries experiencing greater security in project areas (%) (Percentage, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. PHINDIRITBL  Total beneficiaries - female (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 252424.00 252424.00 275000.00 PHINDIRITBL  Total beneficiaries - male (number) (Number, Core Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 245064.00 245064.00 275000.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 8/19/2016 Page 7 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Beneficiaries experiencing greater security in project areas – female (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 13750.00 PHINDIRITBL  Beneficiaries experiencing greater security in project areas – male (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 13750.00 PHINDIRITBL  Increase in number of community members reporting communications with members of a different group (ethnic, religious or different sub-village) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Jul-2012 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments To be measured in end of project assessment. PHINDIRITBL  Community-wide meetings achieve at least 60% participation of households (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments This has proven to be a difficult target to meet, but data is currently being consolidate for the initial set of community-wide meetings held in 2016, so we hope to be able to update these figures soon. 8/19/2016 Page 8 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Number of community-wide meetings in which at least 50% of participants are women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 9.62 9.62 80.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 PHINDIRITBL  Communities with improved local infrastructure facilities and/or livelihood activities implemented by the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 225.00 225.00 277.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments Once implementation commences in the new sites for 2016, this number should increase to over 300 communities. PHINDIRITBL  Beneficiaries that feel project investments reflected their needs (percentage) (Percentage, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 86.00 86.00 60.00 Date 01-Jan-2006 30-Apr-2015 09-Aug-2016 31-Dec-2016 Comments This figure comes from the 2012 independent assessment and will be updated in the 2016/17 independent assessment. PHINDIRITBL  Beneficiaries that feel project inv. reflected their needs - female (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 226981.00 226981.00 134054.00 8/19/2016 Page 9 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Total beneficiaries - female (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 251921.00 251921.00 223424.00 PHINDIRITBL  Total beneficiaries - male (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 244606.00 244606.00 213584.00 PHINDIRITBL  Beneficiaries that feel project inv. reflected their needs - male (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 210117.00 210117.00 128150.00 PHINDIRITBL  Communities with sub-project investments that match one of top three identified priorities (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 30.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 8/19/2016 Page 10 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Number of people's organization members who are women (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 45.74 45.74 40.00 Date 01-Oct-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 PHINDIRITBL  Number of people's organizations with female officers (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 92.00 92.00 92.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 PHINDIRITBL  Community members who reported participation in a collective effort and also reported improved well being (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 38.00 38.00 30.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments This figure comes from the 2012 indepdendent assessment and will be updated following the 2016/17 indepednetn assessment. PHINDIRITBL  Number of project-facilitated meetings conducted without incidents of conflict (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 530.00 530.00 454.00 Date 01-Oct-2006 29-Dec-2015 09-Aug-2016 30-Jun-2015 8/19/2016 Page 11 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Local communities, poeple's organizations and local government units perceive BDA to be a credible development partner (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 67.00 67.00 75.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments This is taken from satisfaction ratings with BDA from the 2012 independent assessment and will be updated following the 2016/17 independent assessment. PHINDIRITBL  Number of BDA and Sajahatra Bangsamoro Project Management Team staff participating in capacity-building sessions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 378.00 378.00 377.00 Date 01-Jan-2007 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments The Sajahatra Bangsamoro program was closed in March 2016. PHINDIRITBL  Program partnerships forged by BDA with other organizations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 13.00 13.00 15.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments This indicator is seen as a measure of BDA's institutional maturity and credibility as it gradually adds partnerships outside MTF, which for a long time was BDA's only development partner and source of funding. 8/19/2016 Page 12 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Percentage of sub-projects with adequate workmanship (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 81.00 81.00 80.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments This figure is based on assessments from the Bank's engineer. It will be updated once he is mobilized to check infrastructure subprojects in the second half of 2016. PHINDIRITBL  Regular monthly and quarterly reports delivered on time by BDA (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 5.00 10.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 PHINDIRITBL  Grievances registered related to delivery of project benefits addressed (%) (Percentage, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 95.20 95.20 100.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 PHINDIRITBL  Grievances related to delivery of project benefits that are addressed (number) (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 21.00 21.00 30.00 8/19/2016 Page 13 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Training sessions provided to people's organizations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 2144.00 2144.00 2172.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments Data for this indicator is still being gathered for training undertaken in 2016. This will be updated shortly. PHINDIRITBL  Number of PO members trained in training sessions (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5717.00 5717.00 5033.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments Data for this indicator is still being gathered for training undertaken in 2016. This will be updated shortly. PHINDIRITBL  Community members perceiving people's organizations as a functional organization (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 84.70 84.70 50.00 Date 01-Jan-2006 29-Dec-2015 09-Aug-2016 31-Dec-2016 Comments The figure for this is a proxy from the 2012 independent assessment and related to satisfaction with the PO, particularly with respect to operations and maintenance. This will be updated following the 201/17 indepdnent assessment. 8/19/2016 Page 14 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Bangsamoro Development Plan delivered with at least five community consultations (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 1.00 Date 14-Nov-2013 29-Dec-2015 09-Aug-2016 30-Dec-2016 Comments The Bangsamoro Development Plan has been delivered with over 30 community consultations at various levels both before and after drafting of the Plan. PHINDIRITBL  Number of people receiving entrepreneurship training and support (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 145.00 1045.00 805.00 Date 11-Dec-2012 29-Dec-2015 09-Aug-2016 31-Oct-2016 PHINDIRITBL  Increase in income for those who start a new enterprise (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 11-Dec-2012 29-Dec-2015 09-Aug-2016 31-Oct-2016 Comments To be assessed in the project impact evaluation. PHINDIRITBL  Number of people who receive employment skills training (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 11-Dec-2012 30-Apr-2015 09-Aug-2016 31-Oct-2016 Comments Due to serious issues on the sustainability of the community enterprise groups, this aspect of the program has not been prioritized. 8/19/2016 Page 15 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) PHINDIRITBL  Percentage of those who receive employment skills training who secure wage employment (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 11-Dec-2012 30-Apr-2015 09-Aug-2016 31-Oct-2016 PHINDIRITBL  Increase in income for those who secure wage employment (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 11-Dec-2012 29-Dec-2015 09-Aug-2016 31-Oct-2016 PHINDIRITBL  Number of common facilities constructed and being used by the community (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 8.00 8.00 11.00 Date 11-Dec-2012 29-Dec-2015 09-Aug-2016 31-Oct-2016 Overall Comments Data on Financial Performance 8/19/2016 Page 16 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P095173 TF-13118 Effective USD 2.43 2.43 0.00 2.43 0.00 100% P095173 TF-56041 Closed USD 1.41 1.40 0.00 1.40 0.00 100% P095173 TF-57067 Closed USD 0.60 0.56 0.04 0.56 0.00 100% P095173 TF-90481 Closed USD 1.14 0.76 0.39 0.65 0.00 85% P095173 TF-91794 Closed USD 0.61 0.60 0.00 0.60 0.00 100% P095173 TF-93781 Effective USD 7.52 7.52 0.00 5.48 2.03 73% P095173 TF-95308 Closed USD 1.15 1.12 0.03 1.13 0.00 101% P095173 TF-95941 Effective USD 9.22 9.22 0.00 8.15 1.08 88% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P095173 TF-13118 Effective 03-Dec-2012 03-Dec-2012 03-Dec-2012 31-Dec-2015 31-Dec-2016 P095173 TF-56041 Closed 29-Dec-2005 29-Dec-2005 30-Mar-2006 31-Dec-2010 31-Dec-2010 P095173 TF-57067 Closed 20-Sep-2006 20-Sep-2006 20-Sep-2006 28-Feb-2010 28-Feb-2010 P095173 TF-90481 Closed 29-Jun-2007 29-Jun-2007 29-Jun-2007 18-Oct-2007 18-Oct-2007 P095173 TF-91794 Closed 21-Apr-2008 21-Apr-2008 21-Apr-2008 29-Oct-2010 31-Oct-2011 P095173 TF-93781 Effective 09-Mar-2009 17-Mar-2009 17-Mar-2009 30-Jun-2010 31-Dec-2016 P095173 TF-95308 Closed 26-Oct-2009 18-Nov-2009 18-Nov-2009 30-Sep-2012 30-Jun-2013 P095173 TF-95941 Effective 08-Jan-2010 13-Jan-2010 13-Jan-2010 30-Jun-2010 31-Dec-2016 Cumulative Disbursements 8/19/2016 Page 17 of 18 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report MULTI DONOR FACILIT Y - PH MINDANAO RECONSTRUCTION & DEVELOPMENT (P095173) Restructuring History Level Approved on 30-Jun-2011 ,Level Approved on 16-Aug-2012 ,Level Approved on 28-Sep-2012 Related Project(s) P132238-Multi Donor Facility - PH Mindanao Reconstruction & Development ,P147008-Multi Donor Facility - PH Mindanao Reconstruction & Development ,P157966-Multi Donor Facility - PH Mindanao Reconstruction & Development 8/19/2016 Page 18 of 18 Public Disclosure Copy