PROCUREMENT PLAN (Textual Part) Project information: Republic of Congo - Commercial Agriculture Project P-159979 Project Implementation agency: Ministry of Agriculture, Livestock and Fisheries Date of the Procurement Plan: October 5, 2017 Period covered by this Procurement Plan (PPA): October 5, 2017 - January 31, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Not applicable Goods: Not applicable Works: Not applicable Other Relevant Procurement Information. Procurement in Situations of Urgent Need of Assistance or Capacity Constraints PROCUREMENT Congo, Republic of : Commercial Agriculture Project PLAN General Information Country: Congo, Republic of Bank’s Approval Date of the Original Procurement Plan: 2017-10-05 2019-06-07 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159979 GPN Date: Project Name: Commercial Agriculture Project Loan / Credit No: IDA / V0400, IDA / 61110 Executing Agency(ies): Commercial Agriculture Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PDAC-0015-T-AON / Single Stage - One Aménagement siège UNCP IDA / 61110 A posteriori Appel d'offres Open - National 102,258.20 Signé 2017-11-28 2017-12-03 2018-01-02 2018-01-07 2018-02-02 2018-06-02 Envelope et ADPS du PDAC CG-PDAC-0082-T-PRIX-18 / Single Stage - One En cours Réhabilitation du circuit IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-04 2018-08-29 2019-02-25 Envelope d'exécution électrique du siège CG-PDAC-0073-T-AON-18 / Entretien piste agricole Les Single Stage - One En cours Saras-Aviation-Bondika (24 IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution km) dans le département du Kouilou CG-PDAC-0072-T-AON-18 / Entretien piste Pilikondi- Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Bilala (38 km), dans le Envelope d'exécution Département du Kouilou CG-PDAC-0071-T-AON-18 / Entretien piste agricole Single Stage - One En cours Mavitou-Lac Cayo (11 km), IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution dans le Département du Kouilou CG-PDAC-0070-T-AON-18 / Entretien piste agricole Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Malolo-Dihessé (27 km), Envelope d'exécution dans le Département du Niari CG-PDAC-0069-T-AON-18 / Entretien Himo piste Single Stage - One En cours agricole Ingah-Ingolo-Mah- IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution Imvouba (35 km), dans le Département du Pool CG-PDAC-0066-T-AON-18 / Entretien piste agricole Boko- Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Ngondzo (18 km), dans le Envelope d'exécution Département du Pool CG-PDAC-0062-T-AON-18 / Entretien piste agricole Single Stage - One En cours Yonon-Ossa-Kialé (18 km), IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution dans le Département des Plateaux Page 1 CG-PDAC-0061-T-AON-18 / Entretien piste agricole Single Stage - One En cours Kibamba-Kidzoumba (28 km), IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution dans le Département de la Bouenza CG-PDAC-0065-T-AON-18 / Entretien Himo piste Single Stage - One En cours agricole Itomba-Eboyo 2 (28 IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution km), dans le Départeemnt des Plateaux CG-PDAC-0063-T-AON-18 / Entretien Himo piste Single Stage - One En cours agricole Djambala-Abala IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution Ndolo (10 km), dans le Département des Plateaux CG-PDAC-0060-T-AON-18 / Entretien piste agricole Single Stage - One En cours Bouansa-Ngouédi/Bretelles IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution (30 km), dans le Département de la Bouenza CG-PDAC-0059-T-AON-18 / Entretien piste agricole Dzouama-Doubandjo-Adingo Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-29 2018-07-04 2018-08-15 2018-09-14 2018-10-19 2019-04-17 (37 km) dans le Envelope d'exécution Département de la Cuvette- Ouest CG-PDAC-0068-T-AON-18 / Entretien piste agricole Single Stage - One En cours Odziba-DzionDzion-Makemba IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution (39 km), dans le Département du Pool CG-PDAC-0067-T-AON-18 / Entretien piste agricole Single Stage - One En cours Massa-Maty centre- Binokina IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution (71 km), dans le Département du Pool CG-PDAC-0085-T-AON-18 / Entretien Himo piste Single Stage - One En cours agricole Makemba-Ingolo IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution (13km) dans le Département du Pool CG-PDAC-0357-T-ED-19 / Travaux-Réhabilitation de la radio rurale d'enyelle dans Passation de le Departement de la IDA / 61110 A posteriori marché de gré à Direct 34,054.00 Signé 2019-04-21 2019-04-26 2019-05-31 2019-11-27 Lokouala avec la Société gré TECHNOLOGY AFRICA TELECOM & INGENEERING TAT CG-PDAC-0375-T-DCF-19 / HIMO-Travaux d'ntretien de Single Stage - One En cours la piste Dzouama-doubandzo- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Adingo dans le Département de la Cuvette-Ouest CG-PDAC-0376-T-DCF-19 / HIMO-Entretien de la piste Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Djambala-Abala-Ndolo dans Envelope d'exécution le Département des Plateaux Page 2 CG-PDAC-0377-T-DCF-19 / HIMO- Travaux d'entretien Single Stage - One En cours de la piste Yonon-Ossa-Kialé IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution dans le Département des Plateaux CG-PDAC-0378-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Odziba-dzion dzion IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Makemba -Ingolo dans le Département du Pool CG-PDAC-0379-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Massa-Maty Centre- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Binokina dans le Département du Pool CG-PDAC-0380-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 la piste Boko6Ngondzo dans Envelope d'exécution le Département du Pool CG-PDAC-0381-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Kindzoumba- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Kibamba dans le Département de la Bouenza CG-PDAC-0382-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Bouansa-Ngouédi- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Kindzaba-Bretelles dans le Département de la Bouenza CG-PDAC-0383-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 la piste Malolo-Dihesse dans Envelope d'exécution le Département du Niari CG-PDAC-0384-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Les Saras-Car IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Mboma/Aviation-Bondika dans le Département du Kouilou CG-PDAC-0385-T-DCF-19 / HIMO-Travaux d'entretien de Single Stage - One En cours la piste Mavitou-Lac Cayo IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution dand le Département du Kuoilou CG-PDAC-0386-T-AON-19 / HIEQ-Travaux d'entretien de Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 la piste Itomba-Eboyo2 dans Envelope d'exécution le Département des Plateaux CG-PDAC-0387-T-AON-19 / HIEQ-Travaux d'entretien de Single Stage - One En cours la piste Ngania-Ngouené- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Okassa dans le Département des Plateaux CG-PDAC-0388-T-AON-19 / HIEQ-Travaux d'entretien de Single Stage - One En cours la piste Ingah-Ingolo-Mah- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Imvouba dans le Département du Pool Page 3 CG-PDAC-0389-T-AON-19 / HIEQ-Travaux confortatifs de Single Stage - One En cours la piste Pilikondi-Bilala- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-24 2019-05-29 2019-07-10 2019-08-09 2019-09-13 2020-03-11 Envelope d'exécution Banga dans le Département du Kouilou CG-PDAC-407-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Mpassi-Mpassi - 6 manguiers Envelope d'exécution dans le Département du Niari CG-PDAC-406-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Dibeni-Mpassi-Mpassi-Maboko Envelope d'exécution dans le Départetement du Niari CG-PDAC-405-T-AO-19 / Réhabilitation-Travaux de Single Stage - One En attente réhabilitation de la piste IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Envelope d'exécution Tsiaki- Mahouobo dans le Département de la Bouenza CG-PDAC-404-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Kayes -Louamba et Envelope d'exécution achevement du pont dans le Département de la Bouenza CG-PDAC-402-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Boko-Mandombé/Bretelles Envelope d'exécution dans le Département du Pool CG-PDAC-400-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente Pamba Odzaka- IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Envelope d'exécution Odzema/Imania-Okombé-Oko dans le Département de la Cuvette CG-PDAC-401-T-AO-19 / Réhabilitation-Travaux de Single Stage - One En attente réhabilitation de la piste IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Envelope d'exécution Ngo 2 - Adzi-Impé dans le Département des Plateaux CG-PDAC-399-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Issabi- Aporo-Mouengué - Envelope d'exécution Ingouala et Ilebé dans le Département de la Cuvette CG-PDAC-415-T-AO-19 / Réhabilitation-Travaux de réhabilitation de la piste Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-14 2019-06-19 2019-07-31 2019-08-30 2019-10-04 2020-04-01 Ewo -Ngami - Bia - Kébili Envelope d'exécution dans le Département de la Cuvette-Ouest Page 4 CG-PDAC-398-T-ED-19 / Réhabilitation-Travaux de réhabilitation du Pont sur la Passation de En attente rivière Lébomi dans le IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-14 2019-06-19 2019-07-24 2020-01-20 d'exécution Département de la Cuvette- gré Ouest en Entente Directe avec la Société MBTP CG-PDAC-393-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Antenne Départementale Envelope d'exécution de Planification et de Suivi du PDAC à Kinkala CG-PDAC-394-T-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Antenne Départementale Envelope d'exécution de Planification et de Suivi du PDAC à NKAYI CG-PDAC-392-T-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Antenne Départementale Envelope d'exécution de Planification et de Suivi du PDAC à NGO CG-PDAC-391-T-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Antenne Départementale Envelope d'exécution de Planification et de Suivi du PDAC à Ouesso CG-PDAC-390-T-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Unité Nationale de Envelope d'exécution Coordination du PDAC à Brazzaville CG-PDAC-395-T-AO-18 / Travaux de réhabilitation et d'Aménagement des bureaux Single Stage - One En attente IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 de l'Antenne Départementale Envelope d'exécution de Planification et de Suivi du PDAC à Pointe-Noire CG-PDAC-408-T-ED-19 / Réhabilitation-Travaux Passation de En attente d'ouverture de la piste IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-14 2019-06-19 2019-07-24 2020-01-20 d'exécution Tchivala-Louvenza avec la gré Societe TRANSLOGISTIQUE CG-PDAC-403-T-ED-19 / Réhabilitation-Travaux de réhabilitation de la piste Passation de En attente Maboria-Odziba dans le IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-14 2019-06-19 2019-07-24 2020-01-20 d'exécution Département du Pool en gré Entente Directe avec la Société CP GOODS Page 5 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PDAC-001-F-CF-17 / Equipements informatiques Single Stage - One En cours IDA / V0400 A posteriori Appel d'offres Limited 0.00 2017-10-10 2017-10-15 2017-11-14 2017-11-19 2017-12-15 2018-02-13 et mobilier de bureau pour Envelope d'exécution l'UNCP et ADPS CG-PDAC-010-F-ED / logiciel-Acquisition du logiciel Passation de de gestion financière et de IDA / V0400 A posteriori marché de gré à Direct 61,172.53 Signé 2017-08-29 2017-09-03 2017-10-24 2017-12-23 suivi évaluation (installation gré paramétrage et formation du personnel CG-PDAC-009-F-ED / Fibre optique-Acquisition de la Passation de connexion Internet par fibre IDA / V0400 A posteriori marché de gré à Direct 26,664.42 Signé 2017-02-01 2017-02-06 2017-03-23 2018-04-30 optique pour l'UNCP du gré PDAC CG-PDAC-0013-F-CF-17 / Equipement informatique et Single Stage - One IDA / 61110 A posteriori Demande de prix Open - National 0.00 Annulé 2017-10-21 2017-12-26 2018-02-24 mobilier de bureau pour Envelope l'UNCP et ADPS du PDAC CG-PDAC-0014-F-ED-17 / Acquisition de la ligne de Passation de connexion internet de IDA / 61110 A posteriori marché de gré à Direct 2,472.68 Signé 2017-10-16 2017-10-19 2017-11-03 2018-10-29 secours pour l'UNCP gré duPDAC CG-PDAC-0016-F-CF-17 / Single Stage - One En cours Confection des enseignes de IDA / 61110 A posteriori Demande de prix Limited 0.00 2017-10-30 2017-12-15 2018-01-14 Envelope d'exécution l'UNCP du PDAC CG-PDAC-0074-F-PRIX-18 / Acquisition internet pour Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-06-05 2018-07-31 2019-01-27 l'Antenne départementale du Envelope d'exécution PDAC à Nkayi CG-PDAC-0077-F-PRIX-18 / Acquisition internet pour Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-03 2018-08-28 2019-02-24 l'Antenne départementale du Envelope d'exécution PDAC à Ngo CG6PDAC-0078-F-PRIX-18 / Acquisition internet pour Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-03 2018-08-28 2019-02-24 l'Antenne départementale du Envelope d'exécution PDAC à Kinkala CG-PDAC-0079-F-PRIX-18 / Acquisition internet de Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-10-05 2018-11-30 2019-05-29 l'Antenne départementale du Envelope d'exécution PDAC à Ouesso CG-PDAC-0080-F-AON-18 / Acquisition des équipements Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 informatiques Envelope d'exécution complémentaires du PDAC CG-PDAC-F-0081-AON-18 / Acquisition du mobilier de Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 bureau pour le personnel Envelope d'exécution complémentaire du PDAC Page 6 CG-PDAC-0088-F-PRIX-18 / Acquisition de 5 tableaux Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-09 2018-09-03 2018-10-03 muraux pour le PDAC et le Envelope d'exécution MAEP. CG-PDAC-0106-F-AON-18 / Acquisition de 6 véhicules de Single Stage - One En cours terrain 4x4 pour l'UNCP et IDA / 61110 A posteriori Appel d'offres Limited 0.00 2018-06-28 2018-07-03 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Envelope d'exécution les antennes de Nkayi et Ouesso du PDAC CG-PDAC-0064-F-PRIX-18 / Acquisition internet pour Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-30 2018-09-24 2019-03-23 l'Antenne départementale du Envelope d'exécution PDAC de Pointe-Noire CG-PDAC-0114-F-PRIX-18 / Single Stage - One En cours Création et hébergement du IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-09-15 2018-10-19 2018-10-26 Envelope d'exécution site Internet du PDAC CG-PDAC-0139-F- PRIX-18 / Acquisition du matériel de Single Stage - One En cours suivi électronique des IDA / 61110 A posteriori Demande de prix Open - National 0.00 2018-12-01 2019-01-26 2019-07-25 Envelope d'exécution prestataires chargés suivi des plans d'affaires en 2019 CG-PDAC-140-F-AON-18 / Acquisition de 100 motos Single Stage - One En cours pour les prestataires chargés IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2018-12-05 2018-12-10 2019-01-21 2019-02-20 2019-03-27 2019-09-23 Envelope d'exécution de suivi et encadrement de plan d'affaires CG-PDAC-0198-PRIX-19 / Acquisition de 5 enseignes pour les Antennes Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2019-01-12 2019-03-09 2019-09-05 départementales de Envelope d'exécution planification et de suivi du PDAC CG-PDAC-138-F-ED-18 / Acquisition d'un système du SE électronique avec une base de données à référence Passation de spéciale pour la collecte de IDA / 61110 A posteriori marché de gré à Direct 60,469.58 Signé 2018-12-20 2018-12-25 2019-01-29 2019-07-28 données sur le suivi des gré effets et impacts du PDAC (formation et assistance des utilisateurs) avec le cabinet OM CONSULTING CG-PDAC-0349-F-ED-19 / Expérimentation des Passation de En cours biofertilisants par avec le IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-03-24 2019-03-29 2019-05-03 2019-10-30 d'exécution groupement des tâcherons au gré Congo-LIAMBOU Giselle CG-PDAC-0355-F-ED-19 / Acquisition de 40 véhicules 4x4 double cabine pour les Passation de En cours Directeurs départementaux IDA / 61110 A priori marché de gré à Direct 0.00 2019-04-18 2019-04-23 2019-05-28 2019-11-24 d'exécution du Ministère de lAgriculture gré de lElevage et de la Peche avec CFAO CONGO CG-PDAC-0368-F-DCF-19 / Acquisition du mobilier de Single Stage - One En cours IDA / 61110 A posteriori Appel d'offres Open - National 0.00 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-03-02 bureau pour le personnel Envelope d'exécution complémentaire du PDAC Page 7 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CG-PDAC-0083-C-PRIX-18 / personnel Entretien réseau Single Stage - One En cours IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-04 2018-08-29 2019-02-25 informatique et internet du Envelope d'exécution PDAC CG-PDAC-0084-C-PRIX-18 / Single Stage - One En cours Personnel entretien matériel IDA / 61110 A posteriori Demande de prix Limited 0.00 2018-07-04 2018-08-29 2019-02-25 Envelope d'exécution informatique du PDAC CG-PDAC-0107-A-ED-18 / RENOUVELLEMENT CONTRAT RELATIF A L'ENTRETIEN DES LOCAUX DE L'UNITE Passation de NATIONALE DE IDA / 61110 A posteriori marché de gré à Direct 2,081.66 Achevé 2018-05-31 2018-06-05 2018-07-10 2019-07-10 COORDINATION DU gré PROJET D'APPUI AU DEVELOPPEMENT DE L'AGRICULTURE COMMERCIALE (PDAC) CG-PDAC-0108-A-ED-18 / RENOUVELLEMENT CONTRAT RELATIF A MAINTENANCE DU GROUPE ELECTROGENE Passation de DE L'UNITE NATIONALE IDA / 61110 A posteriori marché de gré à Direct 1,040.83 Achevé 2018-05-31 2018-06-05 2018-07-10 2019-07-10 DE COORDINATION DU gré PROJET D'APPUI AU DEVELOPPEMENT DE L'AGRICULTURE COMMERCIALE (PDAC) CG-PDAC-0109-A-ED-18 / RENOUVELLEMENT CONTRAT RELATIF AU RAMASSAGE DES ORDURES SOLIDES AU Passation de SIEGE DE L'UNITE IDA / 61110 A posteriori marché de gré à Direct 416.33 Achevé 2018-05-31 2018-06-05 2018-07-10 2019-01-06 NATIONALE DE gré COORDINATION DU PROJET D'APPUI AU DEVELOPPEMENT DE L'AGRICULTURE COMMERCIALE (PDAC) CG-PDAC-0110 / RENOUVELLEMENT CONTRAT RELATIF A LA MAINTENANCE DES PHOTOCOPIEURS DE Passation de L'UNITE NATIONALE DE IDA / 61110 A posteriori marché de gré à Direct 1,040.83 Achevé 2018-05-31 2018-06-05 2018-07-10 2019-01-06 COORDINATION DU gré PROJET D'APPUI AU DEVELOPPEMENT DE L'AGRICULTURE COMMERCIALE (PDAC) Page 8 CG-PDAC-0111-A-ED-18 / RENOUVELLEMENT CONTRAT RELATIF AU SERVICE DE GARIENNAGE Passation de AU SIEGE L'UNITE DE IDA / 61110 A posteriori marché de gré à Direct 7,419.95 Achevé 2018-05-31 2018-06-05 2018-07-10 2019-01-06 COORDINATION DU gré PROJET D'APPUI AU DEVELOPPEMENT DE L'AGRICOLE COMMERCIALE (PDAC) CG-PDAC-410-A-ED-19 / Renouvellement contrat gardienage des locaux de l'Unité de Coordination Passation de En attente Nationale du Projet dAppui IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-06 2019-06-11 2019-07-16 2020-01-12 d'exécution au Developpement de gré lAgriculture Commerciale PDAC avec la société PROSEC CG-PDAC-409-A-ED-19 / Renouvellement contrat entretien des locaux de l'Unité de Coordination Passation de En attente Nationale du Projet dAppui IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-06 2019-06-11 2019-07-16 2020-01-12 d'exécution au Developpement de gré lAgriculture Commerciale PDAC avec Monsieur BITOUALA Donatien CG-PDAC-421-A-ED-19 / Renouvellement contrat maintenance des photocopieurs de lUnité de Passation de Coordination Nationale du En attente IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-06 2019-06-11 2019-07-16 2020-01-12 Projet dAppui au d'exécution gré Developpement de lAgriculture Commerciale PDAC avec MR SENGA Jean CG-PDAC-413-A-ED-19 / Renouvellement contrat maintenance du groupe electrogene de lUnité de Passation de Coordination Nationale du En attente IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-06 2019-06-11 2019-07-16 2020-01-12 Projet dAppui au d'exécution gré Developpement de lAgriculture Commerciale PDAC avec MR POATY Henri Blaise CG-PDAC-411-A-ED-19 / Renouvellement contrat ramassage des ordures solides au siege de l'Unité Passation de de Coordination Nationale En attente IDA / 61110 A posteriori marché de gré à Direct 0.00 2019-06-06 2019-06-11 2019-07-16 2020-01-12 du Projet dAppui au d'exécution gré Developpement de lAgriculture Commerciale PDAC avec lassociation AJCD CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 9 CG-PDAC-002-C-SMC-17 / Etude relative à la situation Sélection au Open - IDA / V0400 A posteriori 0.00 Annulé 2017-10-15 2017-10-30 2017-12-04 2018-01-03 2018-01-08 2018-01-23 2018-02-27 2018-04-08 de référence dans les zones moindre coût International du projet CG-PDAC-003-C-SMC-17 / Filières cibles-Etude de développement de filières Sélection au Open - IDA / V0400 A posteriori 0.00 Annulé 2017-10-10 2017-10-25 2017-11-19 2017-12-19 2017-12-24 2018-01-08 2018-02-05 2018-03-09 cibles ou schéma directeur moindre coût International évolutif vers la préparation du nouveau projet CG-PDAC-005-C-SMC-17 / Vugarisation-Etude sur la Sélection au Open - En cours vulgarisation agricole et les IDA / V0400 A posteriori 0.00 2017-10-12 2017-10-27 2017-11-06 2017-12-16 2017-12-23 2018-01-09 2018-02-13 2018-04-14 moindre coût International d'exécution modalités d'appui aux exploitants agricoles CG-PDAC-011-C-SMC / Manuel-Elaboration du manuel des opérations du Projet (Manuels d'exécution, des procédures Sélection au Open - administratives financière, IDA / V0400 A posteriori 0.00 Annulé 2017-08-01 2017-08-16 2017-09-06 2017-10-16 2017-10-26 2017-11-12 2017-12-17 2018-03-17 moindre coût International comptable, de suivi évaluation, de suivi environnemental et social de gestion à coups partagés, d'intervention urgente CG-PDAC-54019-CS-LCS / Etude relative à la situation Sélection au Open - En cours IDA / 61110 A posteriori 0.00 2018-02-28 2018-03-05 2018-03-23 2018-04-22 2018-04-25 2018-05-05 2018-06-09 2018-09-07 de référence dans les zones moindre coût International d'exécution du Projet CG-PDAC-0035-C-SMC-18 / Recrutement d'un organisme indépendant chargé de d'analyser les plans d'affaires des groupes de Sélection au Open - En cours IDA / 61110 A posteriori 0.00 2018-06-28 2018-07-19 2018-08-05 2018-09-14 2018-09-17 2018-09-27 2018-11-01 2019-10-27 producteurs et des micro, moindre coût International d'exécution petites et moyennes entreprises agroindustrielles candidats aux subventions du projet CG-PDAC-0038-C-SMC-18 / Sélection au Open - En cours Recrutement d'un cabinet IDA / 61110 A posteriori 0.00 2018-07-31 2018-08-15 2018-09-05 2018-09-08 2018-09-15 2018-10-02 2018-10-28 2021-10-12 moindre coût International d'exécution d'audit (Auditeur Externe) CG-PDAC-0086-C-SMC-18 / Recrutement d'un cabinet chargé d'appuyer le MAEP dans l'élaboration des avants Sélection au En cours IDA / 61110 A posteriori Open - National 0.00 2018-07-18 2018-08-08 2018-09-21 2018-10-19 2018-11-18 2018-12-23 2019-01-27 2019-07-26 projets de textes législatifs moindre coût d'exécution et réglementaires des secteurs agro pastoral et halieutique. CG-PDAC-0112-C-SMC-18 / Recrutement d'un cabinet Sélection au Open - En cours IDA / 61110 A posteriori 0.00 2018-07-20 2018-08-10 2018-09-23 2018-10-21 2018-11-20 2018-12-25 2019-01-29 2019-07-28 pour l'élaboration du code moindre coût International d'exécution rural Page 10 CG-PDAC-0358-C-SCBD-19 / ONG-Recrutement dune ONG chargee de la selection et de la gestion des prestataires Sélection dans le de montage et de suivi En cours IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 encadrement des plans d'exécution déterminé d'affaires campaggne 2020 dans les departements du Kouilou Pointe-Noire et Niari CG-PDAC-0359-C-SCBD-19 / ONG-Recrutement dune ONG chargee de la selection et de la gestion des prestataires Sélection dans le En cours de montage et de suivi IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 d'exécution encadrement des plans déterminé d'affaires campaggne 2020 dans les departements de la Bouenza et la Lekoumou CG-PDAC-0360-C-SCBD-19 / ONG-Recrutement dune ONG chargee de la selection et de la gestion des prestataires Sélection dans le En cours de montage et de suivi IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 d'exécution encadrement des plans déterminé d'affaires campaggne 2020 dans les departements du Pool et de Brazzaville CG-PDAC-0361-C-SCBD-19 / ONG-Recrutement dune ONG chargee de la selection et de la gestion des prestataires Sélection dans le de montage et de suivi En cours IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 encadrement des plans d'exécution déterminé d'affaires campaggne 2020 dans les departements des Plateaux Cuvette et Cuvette Ouest CG-PDAC-0362-C-SCBD-19 / ONG-Recrutement dune ONG chargee de la selection et de la gestion des prestataires Sélection dans le En cours de montage et de suivi IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 d'exécution encadrement des plans déterminé d'affaires campaggne 2020 dans les departements de la Sangha et de la Likouala CG-PDAC-0365-C-SQC-19 / Etude-Etude dimpact environnemental et social Sélection fondée pour la rehabilitation et sur les En cours IDA / 61110 A posteriori Open - National 0.00 2019-04-18 2019-05-09 2019-06-22 2019-07-22 2019-08-26 2020-02-22 lamenagement des sites de qualifications des d'exécution lInstitut de Recheche consultants Agronomique-IRA a Loudima et Oyo CG-PDAC-0369-C-SBD-19 / Sélection dans le Recrutement ONG pour le En cours IDA / 61110 A posteriori cadre d'un budget Open - National 0.00 2019-05-15 2019-06-05 2019-07-19 2019-08-16 2019-09-15 2019-10-20 2019-11-24 2020-11-23 suivi des plans daffaires des d'exécution déterminé populations autochtones CG-PDAC-0367-C-SQC-19 / Etude d'impact Sélection fondée environnementale et sociale sur les En attente IDA / 61110 A posteriori Limited 0.00 2019-06-14 2019-06-28 2019-07-28 2019-09-01 2020-02-28 pour la réhabilitation des qualifications des d'exécution pistes et des ouvrages consultants franchissement à réhabiliter Page 11 INDIVIDUAL CONSULTANTS Page 12