The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) Road Upgrading and Development Project (P149955) EUROPE AND CENTRAL ASIA | North Macedonia | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 6 | ARCHIVED on 25-Jun-2019 | ISR37578 | Implementing Agencies: Public Enterprise for State Roads, Ministry of Finance, Public Enterprise for State Roads Key Dates Key Project Dates Bank Approval Date: 30-Sep-2015 Effectiveness Date: 30-Dec-2015 Planned Mid Term Review Date: 01-Oct-2019 Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2020 Revised Closing Date: 31-Dec-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objectives are to improve transport connectivity for road users along Corridor VIII between Skopje and DeveBair, and to improve the asset management and planning functions of Public Enterprise for State Roads. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Construction along Corridor VIII: Rankovce - Kriva Palanka:(Cost $85.50 M) Institutional and Project Implementation Support:(Cost $5.50 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions Construction on both lots of Corridor VIII between Kriva Palanka and Rankovce is underway but physical progress needs to be accelerated during the summer period. Procurement of the bridge management system (BMS) is also in delay. The Public Enterprise for State Roads (PESR) has improved quality aspects in managing environmental and social safeguards and this needs to be maintained. 6/25/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) 6/25/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Moderate Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Moderate Moderate Moderate Fiduciary Low Low Low Environment and Social Substantial Substantial Substantial Stakeholders Low Low Low Other Moderate Moderate Moderate Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improve transport connectivity for road users along Corridor VIII between Skopje and Deve Bair IN00715178 ►Volume of freight along Corridor VIII (tones, section Rankovce - Kriva Palanka) (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target 6/25/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) Value 43.80 43.80 43.80 45.00 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 Indicator to be updated on completion of new sections and retains baseline value for now Comments: IN00715179 ►Market accessibility index along Corridor VIII (section Rankovce - Kriva Palanka) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 138.50 138.50 138.50 265.60 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 Indicator to be updated on operation of new road sections and retains baseline value for now Comments: IN00715180 ►Vehicle operating cost for road users, in Euro per vehicle-km, along the project road section. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.12 1.12 1.12 0.92 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 Indicator to be updated on completion of new sections and retains baseline value for now Comments: Improve the Borrower's asset management and planning function IN00715177 ►Bridge maintenance and investment program developed based on Bridge Management System (BMS). (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 Intermediate Results Indicators by Components Construction along Corridor VIII: Rankovce - Kriva Palanka IN00715236 ►Roads constructed, non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 24.64 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 IN00715238 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/25/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) Value 6,181.00 6,181.00 6,181.00 0.00 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 The number of beneficiaries is calculated as a weighted sum [times average occupancy] of buses (x20), passenger vehicles (x2.2), and trucks (x1) . The number is on daily basis. Frequency of vehicles Comments: measured with automatic traffic data counters. Indicator to be updated on completion of new sections and retains baseline value for now IN00715241 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 47.00 0.00 0.00 IN00715242 ►Percentage of beneficiaries expressing satisfaction with condition of the project roads (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 52.00 52.00 52.00 0.00 Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 Baseline and actual value is determined by the ex ante assessment in 2017. Ex post beneficiary Comments: assessment with same communities will be done once the road is completed. IN00715243 ►Citizen Input to PESR during preparation and construction of the project. (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Citizens' inputs on over- Citizens' inputs on & underpasses included over- & underpasses Citizen committees Final Citizen’s Value in design. Grievance included in design. formed engagement report Redress Mechanism Grievance Redress exists. Mechanism exists. Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2020 During the preparation of the technical designs PESR had consultations in the two municipalities. Then subsequent consultations were organized for the ESIA and the RAP. Most of the inputs during the meetings were on the underpasses / overpasses for the communities; these were incorporated in final technical designs for both lots. Additional technical designs are under preparation for further improvement of local accesses. Comments: During the implementation GRM has been established to address issues that might be raised during the construction works. Communities can access GRM directly by contacting PESR or through site supervisor and the contractor. Contact information is available in the local government premises and in the public spaces in the villages. Institutional and Project Implementation Support IN00715237 ►Bridge condition survey completed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2018 Comments: End target needs to be revised following the MidTerm Review 6/25/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) IN00715239 ►Digitize all bridge structures as part of the larger digitized national road reference system (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2017 End target needs to be revised following the MidTerm Review Comments: IN00715240 ►Preparation of bridge maintenance and investment plan using the established BMS (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 04-May-2015 07-Dec-2018 17-May-2019 31-Dec-2019 End target needs to be revised following the MidTerm Review Comments: Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P149955 IBRD-85250 Effective USD 90.95 90.95 0.00 18.95 73.32 21% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P149955 IBRD-85250 Effective 30-Sep-2015 06-Oct-2015 30-Dec-2015 31-Dec-2020 31-Dec-2020 Cumulative Disbursements 6/25/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Road Upgrading and Development Project (P149955) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/25/2019 Page 7 of 7