PROCUREMENT PLAN (Textual Part) Project information: Social Protection Integration (P152057) Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT Honduras : Social Protection Integration PLAN General Information Country: Honduras Bank’s Approval Date of the Original Procurement Plan: 2019-07-29 2019-07-29 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152057 GPN Date: 2019-07-29 Project Name: Social Protection Integration Loan / Credit No: IDA / 64010 Executing Agency(ies): Subsecretaria de Integración Social (SSIS) WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Institutional strengthening HN-SSIS-121912-GO-RFQ / for the CCT Program and Solicitud de Single Stage - One Ejecución 2.1.6 Adquisicion de IDA / 64010 Posterior Open - National 500.00 0.00 2020-02-05 2020-03-19 2020-05-23 Integration of the Social cotizaciones Envelope pendiente Certificados Digitales Protection System HN-SSIS-121913-GO-RFB / 2.1.44 Adquisición de Planta Telefónica SIP con Institutional strengthening condiciones del Call Center for the CCT Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 80,000.00 0.00 2020-02-10 2020-02-12 2020-03-18 2020-04-01 2020-04-22 2020-06-21 (Equipo de Comunicaciones, Integration of the Social ofertas Envelope pendiente perifericos) para el Protection System fortalecimiento de la Unidad de Atención a Participantes HN-SSIS-121914-GO-RFQ / Institutional strengthening 2.1.45 Equipamiento para el for the CCT Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 10,000.00 0.00 2020-02-12 2020-03-26 2020-05-25 fortalecimiento de la Unidad Integration of the Social cotizaciones Envelope pendiente de Atención a Participantes Protection System HN-SSIS-121915-GO-RFQ / Institutional strengthening 2.2.28 Proyectores para for the CCT Program and Solicitud de Single Stage - One Ejecución fortalecer la capacidad del IDA / 64010 Posterior Open - National 15,000.00 0.00 2020-02-05 2020-03-19 2020-05-18 Integration of the Social cotizaciones Envelope pendiente levantamiento de información Protection System (15) HN-SSIS-122094-GO-RFQ / 2.2.29 Escáner de alto Institutional strengthening rendimiento para garantizar for the CCT Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 12,000.00 0.00 2020-02-09 2020-03-23 2020-05-22 la digitalización de los Integration of the Social cotizaciones Envelope pendiente documentos de respaldo de Protection System las FSU Institutional strengthening HN-SSIS-122107-GO-RFQ / for the CCT Program and Solicitud de Single Stage - One Ejecución 2.2.30 Cintas de respaldo IDA / 64010 Posterior Open - National 12,000.00 0.00 2020-02-04 2020-03-18 2020-05-17 Integration of the Social cotizaciones Envelope pendiente para Backup, CD y DVD Protection System Page 1 HN-SSIS-122145-GO-RFB / (1.2.16, 2.1.14, 2.1.16, 2.1.17, Strengthening of the Urban 2.1.19, 2.2.22, 2.2.24, 2.2.27) Conditional Cash Transfer Adquisición de Equipo Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 191,600.00 0.00 2020-02-03 2020-02-05 2020-03-11 2020-03-31 2020-04-21 2020-07-20 Informático, Licenciamientos, Implementation of the ofertas Envelope pendiente Servidores y sus partes, Integrated Transition Certificados de Seguridad, Strategy Equipo para respaldo, etc. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Strengthening of the Urban HN-SSIS-119661-NC-RFQ / Conditional Cash Transfer 1.1.2. Mecanismo de Pago de Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Previa Open - National 106,119.72 0.00 2019-09-25 2019-11-07 2020-01-06 Comisión por entrega de Implementation of the cotizaciones Envelope pendiente TMC (año 1) Integrated Transition Strategy HN-SSIS-121850-NC-RFQ / Institutional strengthening 2.1.24 Reproducción para la for the CCT Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 25,000.00 0.00 2020-08-13 2020-09-25 2020-11-24 Implementación para la Integration of the Social cotizaciones Envelope pendiente estrategia de comunicaciones Protection System HN-SSIS-121875-NC-RFQ / 2.2.4 Material de Institutional strengthening Reproduccion para la for the CCT Program and Solicitud de Single Stage - One Ejecución IDA / 64010 Posterior Open - National 1,500.00 0.00 2020-08-05 2020-09-17 2020-11-16 Actualizaccion y Socializacion Integration of the Social cotizaciones Envelope pendiente de la Politica de Proteccion Protection System Social Institutional strengthening HN-SSIS-122130-NC-RFB / for the CCT Program and Solicitud de Single Stage - One Ejecución 2.1.7 Servicio de mensajería IDA / 64010 Posterior Open - National 50,000.00 0.00 2020-03-15 2020-05-14 Integration of the Social ofertas Envelope pendiente de texto Protection System CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SSIS-120999-CS-QCBS / 3.10 Revisión de Selección basada Ejecución IDA / 64010 Project Management Posterior Open - National 255,000.00 0.00 2019-09-30 2019-10-14 2019-11-08 2019-12-06 2019-12-26 2020-01-05 2020-02-09 2020-12-22 Cumplimiento proceso en calidad y costo pendiente Operativos año 1 y año 2 HN-SSIS-121253-CS-QCBS / Institutional strengthening 2.1.1 Evaluación de Impacto for the CCT Program and Selección basada Open - Ejecución (Levantamineto, Supervisión, IDA / 64010 Previa 500,000.00 0.00 2019-09-23 2019-10-03 2019-10-25 2019-11-24 2019-12-04 2019-12-24 2020-01-14 2020-04-13 Integration of the Social en calidad y costo International pendiente Análisis y Difusión de Protection System Resultados) HN-SSIS-121855-CS-QCBS / Institutional strengthening 1.2.20 Capacitadores for the CCT Program and Selección basada Open - Ejecución IDA / 64010 Previa 1,500,000.00 0.00 2020-06-01 2020-06-22 2020-07-17 2020-08-14 2020-09-03 2020-09-13 2020-10-18 2020-12-31 Operativos (Supervisados a Integration of the Social en calidad y costo International pendiente través de INFOP) Protection System HN-SSIS-121886-CS-CQS / 2.1.3 Contratación de firma Institutional strengthening Selección basada para la evaluación de for the CCT Program and Ejecución IDA / 64010 Posterior en calificaciones Open - National 50,000.00 0.00 2020-02-09 2020-03-01 2020-04-14 2020-05-14 2020-06-18 2020-12-15 procesos y resultados de la Integration of the Social pendiente de consultores estrategia de transición y Protection System entrega del Bono Urbano Page 2 HN-SSIS-121909-CS-QCBS / Institutional strengthening 2.2.21 Certificación del for the CCT Program and Selección basada Ejecución IDA / 64010 Posterior Open - National 178,000.00 0.00 2020-04-20 2020-05-04 2020-05-29 2020-06-26 2020-07-16 2020-07-26 2020-08-30 2020-12-31 Registro Unico de Integration of the Social en calidad y costo pendiente Participantes RUP Protection System HN-SSIS-123535-CS-QCBS / 3.9 Auditoría financiera y Selección basada Ejecución IDA / 64010 Project Management Posterior Open - National 375,000.00 0.00 2020-06-01 2020-06-15 2020-07-10 2020-08-07 2020-08-27 2020-09-06 2020-10-11 2020-12-22 administrativa externa (años en calidad y costo pendiente 1,2,3,4,5) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HN-SSIS-121853-CS-INDV / Institutional strengthening 2.1.53 Revisión y Rediseño for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 30,000.00 0.00 2020-04-20 2020-05-19 2020-05-21 2020-06-10 2020-12-31 de las capacitaciones temas Integration of the Social pendiente de emprendedurismo. Protection System HN-SSIS-121854-CS-INDV / Institutional strengthening 2.2.1 Consultoria sobre el for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 20,000.00 0.00 2020-02-24 2020-03-24 2020-03-26 2020-04-15 2020-12-31 estado del Sistema de Integration of the Social pendiente Protección Social. Protection System HN-SSIS-121860-CS-INDV / Institutional strengthening 2.1.55(R) Automatización de for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-03-16 2020-04-14 2020-04-16 2020-05-06 2020-12-31 Procesos a (Sistema de Integration of the Social pendiente Información) Protection System Strengthening of the Urban HN-SSIS-121868-CS-INDV / Conditional Cash Transfer 1.2.21 Investigación para la Program and Ejecución definición de los perfiles IDA / 64010 Posterior Individual Open 18,000.00 0.00 2020-03-02 2020-03-31 2020-04-02 2020-04-22 2020-12-31 Implementation of the pendiente para el otorgamiento de Integrated Transition crédito Strategy Strengthening of the Urban HN-SSIS-121872-CS-INDV / Conditional Cash Transfer 1.2.18 Creación y Diseño de Program and Ejecución IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-01-30 2020-02-28 2020-03-01 2020-03-21 2020-12-31 los Modelos de Otorgamiento Implementation of the pendiente de Crédito Integrated Transition Strategy Strengthening of the Urban HN-SSIS-121874-CS-INDV / Conditional Cash Transfer 1.2.17 Adaptación de la Program and Ejecución metodología de otorgamiento IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-07-10 2020-08-08 2020-08-10 2020-08-30 2020-12-31 Implementation of the pendiente de crédito y asistencia Integrated Transition técnica Strategy Strengthening of the Urban HN-SSIS-121877-CS-INDV / Conditional Cash Transfer 1.2.19 Consultoría para la Program and Ejecución evaluación y seguimiento del IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-07-20 2020-08-18 2020-08-20 2020-09-09 2020-12-31 Implementation of the pendiente piloto de otorgamiento de Integrated Transition crédito Strategy HN-SSIS-121882-CS-INDV / Institutional strengthening 2.2.2 Consultoria para la for the CCT Program and Ejecución Elaboración de la Política de IDA / 64010 Posterior Individual Open 15,000.00 0.00 2020-03-16 2020-04-14 2020-04-16 2020-05-06 2020-12-31 Integration of the Social pendiente Protección Social con su Protection System Plan de Implementación. Page 3 HN-SSIS-121887-CS-INDV / 2.1.4 Consultoria para la Institutional strengthening evaluación de funcionamiento for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 25,000.00 0.00 2019-10-18 2019-11-16 2019-11-18 2019-12-08 2019-12-20 del SIG Base de Datos y Integration of the Social pendiente verificación y subsanación de Protection System hallazgos de auditoria HN-SSIS-121890-CS-INDV / Institutional strengthening 2.1.5 Consultoria para la for the CCT Program and Ejecución evaluación de funcionamiento IDA / 64010 Posterior Individual Open 18,000.00 0.00 2019-10-18 2019-11-16 2019-11-18 2019-12-08 2019-12-31 Integration of the Social pendiente del SIG (Infraestructura y Protection System Seguridad) HN-SSIS-121898-CS-INDV / Institutional strengthening 1.2.5 Acompañamiento Social for the CCT Program and Ejecución para la calidad de los IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-02-24 2020-03-18 2020-03-25 2020-04-15 2020-12-31 Integration of the Social pendiente Servicios Educativos del Protection System IHER HN-SSIS-121902-CS-INDV / 2.2.3 Consultoria sobre el Institutional strengthening desarrollo de un sistema de for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 15,000.00 0.00 2020-04-01 2020-04-30 2020-05-02 2020-05-22 2020-12-31 planeación estratégica y Integration of the Social pendiente evaluación de la política Protection System social HN-SSIS-121901-CS-INDV / 1.2.10 Revisión de la Institutional strengthening curricula de orientación for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-01-28 2020-02-27 2020-03-05 2020-03-26 2020-09-22 vocacional y diseño del Integration of the Social pendiente material didáctico para Protection System capacitación a docentes HN-SSIS-121903-CS-INDV / 2.2.11 Consultoria para la implementación del Sistema Institutional strengthening Unico de Evaluación de for the CCT Program and Ejecución Políticas Públicas Sociales IDA / 64010 Posterior Individual Open 20,000.00 0.00 2020-04-01 2020-04-30 2020-05-02 2020-05-22 2020-12-31 Integration of the Social pendiente (SUEPPS) para el Protection System seguimiento de la política de protección social y sus programas sociales HN-SSIS-121904-CS-INDV / 2.2.12 Consultoria para la Institutional strengthening recolección y ponderación for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-04-13 2020-05-12 2020-05-14 2020-06-03 2020-12-31 (justificada) de la Política Integration of the Social pendiente Pública Social en el Protection System SUEPPS HN-SSIS-121905-CS-INDV / 2.2.15 Consultoría para Institutional strengthening diagnóstico del ecosistema y for the CCT Program and Ejecución necesidades de formación de IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-02-17 2020-03-17 2020-03-19 2020-04-08 2020-12-31 Integration of the Social pendiente la estrategia de inclusión Protection System financiera para el Sector Social HN-SSIS-121906-CS-INDV / Institutional strengthening 2.2.16 Consultoria de for the CCT Program and Ejecución homologación de IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-03-10 2020-04-08 2020-04-10 2020-04-30 2020-12-31 Integration of the Social pendiente instrumentos de capacitación Protection System y comunicación de la ENIF HN-SSIS-121907-CS-INDV / Institutional strengthening 2.2.17 Consultoria diseño y for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-03-10 2020-04-08 2020-04-10 2020-04-30 2020-12-31 desarrollo de materiales de Integration of the Social pendiente comunicación y educativos Protection System Page 4 HN-SSIS-121910-CS-INDV / 1.2.14 Diseño y diagramacion Institutional strengthening del Manual para la for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 10,000.00 0.00 2020-06-01 2020-07-01 2020-07-08 2020-07-29 2020-12-31 formación emprendedores ( Integration of the Social pendiente actualización 3ero y 4to Protection System años) HN-SSIS-122108-CS-INDV / 2.1.22 Contratación de Institutional strengthening consultoría para la definición for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 30,000.00 0.00 2019-10-14 2019-11-12 2019-11-14 2020-01-02 2020-12-31 de la estrategia de Integration of the Social pendiente Comunicación del Programa Protection System zona urbana HN-SSIS-122121-CS-INDV / Institutional strengthening 2.1.23 Apoyo a la estrategia for the CCT Program and Ejecución de comunicación del IDA / 64010 Posterior Individual Open 30,000.00 0.00 2020-02-10 2020-03-10 2020-03-12 2020-04-01 2020-12-31 Integration of the Social pendiente programa en modalidad Protection System urbana y rural HN-SSIS-122127-CS-INDV / 2.1.28 Contratación de Institutional strengthening estudios para la for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 25,000.00 0.00 2020-02-20 2020-03-20 2020-03-22 2020-04-11 2020-12-31 homologación de la Integration of the Social pendiente estrategia de inclusión Protection System productiva en zonas rurales HN-SSIS-122128-CS-INDV / 2.1.36 Tres (3) Consultores Institutional strengthening para la formación y for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 27,936.00 0.00 2020-08-10 2020-09-08 2020-09-10 2020-09-30 2020-12-31 supervisión de los gestores Integration of the Social pendiente en orientación vocacional y Protection System empleo HN-SSIS-122129-CS-INDV / Institutional strengthening 2.1.37 Consultoría para el for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 20,000.00 0.00 2020-02-06 2020-02-26 2020-02-28 2020-03-19 2020-12-31 diseño de la estrategia de Integration of the Social pendiente orientación financiera Protection System HN-SSIS-122131-CS-INDV / 2.1.47 Consultoría para el Institutional strengthening diseño y diagramación del for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 15,000.00 0.00 2020-02-10 2020-03-10 2020-03-12 2020-04-01 2020-12-31 material didáctico para Integration of the Social pendiente capacitación a Gestores Protection System Sociales y Guías de Familia HN-SSIS-122132-CS-INDV / Institutional strengthening 2.1.42 Evaluación de la for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 30,000.00 0.00 2020-08-01 2020-08-30 2020-09-01 2020-09-21 2020-12-31 estrategia de orientación Integration of the Social pendiente financiera Protection System HN-SSIS-122134-CS-INDV / 2.1.43 Consultoría para la Institutional strengthening implementación del call for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 15,000.00 0.00 2020-04-27 2020-05-26 2020-05-28 2020-06-17 2020-12-31 center (diagnóstico e Integration of the Social pendiente implementación) (tecnológico Protection System y procesos) HN-SSIS-123517-CS-INDV / 2.1.40 Contratación de Institutional strengthening consultoría para la for the CCT Program and Ejecución IDA / 64010 Posterior Individual Open 15,000.00 0.00 2020-03-02 2020-03-31 2020-04-02 2020-04-22 2020-12-31 diagramación del Material de Integration of the Social pendiente didáctico de orientación Protection System financiera Page 5