Procurement Plan Details of the Procurement Arrangements Involving International Competition 1. Goods, Works, and Non Consulting Services (i) List of contract packages to be procured: Prior review thresholds: Method Levels Comments 1. Goods >=US$2,000,000 Prior review 3. Works >= US$10,000,000 Prior review 5. Direct Contracting All contracts Prior review 1 2 3 4 5 6 7 8 9 Review Estimated Expected Domestic by Ref. Contract Cost Procurement Bid- P-Q Preference Bank Comments No. (Description) (USD Method Opening (yes/no) (Prior Million) Date / Post) Transmission Line ICB/ Kayes- 83.60 ICB No No Prior 06/30/2017 Nr Tambacounda Transmission Line and associated Substations at Kayes and Tambacounda Common Infrastructure ICB/ SCADA 10.4 ICB No No Prior 02/28/2017 Nr System (ii) ICB contracts estimated to cost above US$ 10,000,000 per contract for civil works and US$ 2,000,000 for goods and non-consultancy services and all direct contracting will be subject to prior review by the Bank. 2. Consulting Services Prior review thresholds: Selection method Prior review level Comments 1. Selection of firms >= US$1,000,000 Prior review 2. Selection of individual consultants >= US$300,000 Prior review 3. Single source for firms and individual consultants All contracts Prior review 1 2 3 4 5 6 7 Estimated Review Expected Ref. Cost Selection by Bank Proposals Description of Assignment Comments No. (USD Method (Prior / Submission Million) Post) Date 01/CS Owner’s Engineer 6.00 QCBS Prior 09/30/2017 PROCUREMENT Western Africa : OMVS - TRANSMISSION EXPANSION PROJECT PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2017-03-08 2020-01-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147921 GPN Date: Project Name: OMVS - TRANSMISSION EXPANSION PROJECT Loan / Credit No: IDA / 60330, / Executing Agency(ies): SOGEM WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 01 - TVX/SOGEM 2017 / Travaux de renforcement du RIMA Reinforcement and Open - Single Stage - One réseau des lignes Kayes- IDA / 60330 A priori Appel d'offres 83,600,000.00 40,411,136.58 Signé 2017-07-14 2017-07-19 2017-08-30 2017-09-19 2017-10-24 2019-04-17 Expansion International Envelope Tambacounda et poste associé (Manantali II) CRM2-T2 / Exécution des travaux de renforcement du RIMA Reinforcement and Single Stage - One En attente réseau Câble de garde à IDA / 60330 A posteriori Appel d'offres Open - National 5,880,000.00 0.00 2020-08-10 2020-08-15 2020-09-14 2020-09-24 2020-10-18 2021-10-18 Expansion Envelope d'exécution fibre optique (CGFO) du RIMA GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ML-SOGEM-64877-GO-RFQ / Acquisition d'un véhicule RIMA Reinforcement and Single Stage - One tout terrain 4x4 pour la IDA / 60330 A posteriori Demande de prix Limited 100,000.00 68,477.81 Achevé 2018-06-07 2018-07-08 2018-08-07 Expansion Envelope Coordination Régionale du Projet CRM2-F1 / Fourniture et livraison d'un groupe Single Stage - One En attente électrogène 33 KVA avec IDA / 60330 Technical Assistance A posteriori Demande de prix Limited 18,000.00 0.00 2019-12-08 2020-01-03 2020-01-13 Envelope d'exécution inverseur automatique et forfait installation CRM2-F2 / Fourniture, installation essais et mise en service de RIMA Reinforcement and Open - Single Stage - One En attente transformateurs 225/30 KV; IDA / 60330 A priori Appel d'offres 10,500,000.00 0.00 2020-03-10 2020-03-15 2020-04-26 2020-05-10 2020-06-03 2021-06-03 Expansion International Envelope d'exécution 20 et 40 MVA dans les postes de Matam, Bakel et Dagana CRM2-F3 / Fourniture et essais d'une station mobile RIMA Reinforcement and Open - Single Stage - One En attente de 225/90/30 KV-30MVA au IDA / 60330 A priori Appel d'offres 2,520,000.00 0.00 2019-12-10 2019-12-15 2020-01-26 2020-02-09 2020-03-04 2020-12-29 Expansion International Envelope d'exécution poste HT OMVS /SOGEM de Dagana CRM2-F4 / Fourniture, livraison et essais d'un RIMA Reinforcement and Open - Single Stage - One En attente camion de lavage de ligne IDA / 60330 A priori Appel d'offres 2,000,000.00 0.00 2019-12-10 2019-12-15 2020-01-26 2020-02-09 2020-03-04 2020-12-29 Expansion International Envelope d'exécution HT sous tension au poste HT/OMVS/SOGEM de Sakal. Page 1 01 SOGEM 2017 / Fourniture et installation du RIMA Reinforcement and Open - Single Stage - One / A priori Appel d'offres 10,400,000.00 0.00 Annulé 2017-04-23 2017-04-25 2017-06-06 2017-06-26 2017-07-24 2018-07-24 système de communication et Expansion International Envelope télécommande SCADA ML-SOGEM-64696-GO-RFQ / Acquisition d'un véhicule RIMA Reinforcement and Single Stage - One tout terrain 4x4 pour la IDA / 60330 A posteriori Demande de prix Limited 100,000.00 0.00 Annulé 2018-06-07 2018-07-12 2018-08-11 Expansion Envelope Coordination Régionale du Projet NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 02 CONSOGEM/2017 / Sélection d'un consultant pour les études et le suivi Sélection fondée RIMA Reinforcement and Open - des travaux de renforcement IDA / 60330 A priori sur la qualité et 6,000,000.00 1,591,224.16 Signé 2017-03-03 2017-04-11 2017-04-28 2017-06-09 2017-06-19 2017-07-17 2017-08-06 2019-04-28 Expansion International du réseau des lignes Kayes- le coût Tambacounda et poste associé (Manantali II) ML-SOGEM-54053-CS-CQS / Consultant pour l'élaboration Sélection fondée et la mise en œuvre des sur les Open - Plans d'Action de IDA / 60330 Technical Assistance A posteriori 100,000.00 252,454.82 Signé 2018-03-20 2018-04-10 2018-05-04 2018-05-14 2018-06-18 2018-12-15 qualifications des International Réinstallation (PAR) des consultants populations impactées par la ligne Kayes-Tamba CRM2-C8 / Sélection d'un consultant pour l'étude et le Sélection fondée Open - En attente suivi des travaux relatifs au IDA / 60330 Technical Assistance A priori sur la qualité et 1,000,000.00 0.00 2020-02-28 2020-03-13 2020-04-02 2020-05-02 2020-05-15 2020-06-08 2020-06-25 2021-06-25 International d'exécution renforcement du réseau le coût CGFO du RIMA CRM2-C10 / Sélection d'un consultant pour l'appui à Sélection fondée l'identification de projet et sur les En attente l'assistance à la mise en IDA / 60330 Technical Assistance A posteriori Open - National 100,000.00 0.00 2020-03-16 2020-03-21 2020-04-18 2020-05-02 2020-05-19 2020-09-16 qualifications des d'exécution oeuvre de projet de consultants développement local et d'autonomisation des femmes Sélection fondée ML-SOGEM-32310-CS-CQS / sur les Open - sélection d'un expert pour la IDA / 60330 Technical Assistance A posteriori 125,000.00 0.00 Annulé 2017-10-16 2017-10-26 2017-11-15 2017-11-20 2019-11-15 2019-11-15 qualifications des International sauvegarde environnementale consultants Page 2 CRM2-C11 / Sélection d'un consultant pour la supervision du marché de fourniture, installation, Sélection fondée En attente essais et mise en service des IDA / 60330 Technical Assistance A posteriori sur la qualité et Open - National 504,000.00 0.00 2020-02-27 2020-03-05 2020-04-02 2020-05-02 2020-05-12 2020-06-05 2020-06-25 2021-09-18 d'exécution transformateurs 225/30 kV, le coût 20 et 40 MVA pour les postes HT de Bakel, Matam et Dagana INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CRM2-C7 / Sélection d'un consultant individuel pour l'évaluation technique et En attente financière des propositions IDA / 60330 Technical Assistance A posteriori Individuel Open 67,200.00 0.00 2019-12-05 2020-01-07 2020-01-17 2020-01-27 2020-05-26 d'exécution d'activités supplémentaires dans le cadre de financement de l'IDA. CRM2-C9 / Sélection d'un consultant individuel pour En attente IDA / 60330 Technical Assistance A posteriori Individuel Limited 30,000.00 0.00 2020-02-13 2020-02-23 2020-03-15 2020-03-23 2020-03-25 l'assistance technique dans d'exécution la mise en oeuvre du PAR CRM2-C12 / sélection d'un consultant individuel pour la supervision des marchés de fourniture du camion de En attente IDA / 60330 Technical Assistance A posteriori Individuel Open 85,000.00 0.00 2020-02-27 2020-03-31 2020-04-10 2020-04-26 2020-07-25 lavage de ligne HT sous d'exécution tension et la station mobile 225/90/30 kV-30 MVA à Sakal et Dagana Page 3