Dam Operational Improvement and Safety Project Phase 2 (DOISP 2) LOAN NO. P 8711 Procurement Plan Version No.: 1 Date: July 16, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Ministry of Finance (MOF) c. Project Name: Dam Operational Improvement and Safety Project Phase 2 d. Project Implementing Agency (PIA): (i) Directorate General of Water Resources – Ministry of Public Works and Housing 2. Bank’s No Objection Date of the Procurement Plan: a. Version 1: June 5, 2017 b. Version 2: November 10, 2017 c. Version 3: July 5, 2018 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: January 1, 2017 to December 31, 2018 II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Ref. Bank’s Review Procurement Method Method No. Requirement Threshold 1. International Competitive Bidding ≥ $2,000,000 Each contract equal to or (Goods/IT System) above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 2. International Competitive Bidding ≥ $10,000,000 Each contract equal to or (Non-consulting Services) above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 3. National Competitive Bidding < $2,000,000 Each contract equal to or (Goods/IT System) above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 4. National Competitive Bidding < $10,000,000 Each contract equal to or (Non-consulting Services) above $1,500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. 5. Shopping (Goods/IT System) < $ 100,000 No prior review (only post review). 6. Shopping (Small Works and Non- < $ 200,000 No prior review (only consulting Services) post review). 7. Direct Contracting (Small Works, No procurement Each contract equal to or Goods and Non-consulting method above $1,500,000 Services) threshold. equivalent shall be Subject to subject to Bank’s prior justification for review. All other contracts subject to post Direct review. Contracting as per para. 3.6 of Justification for proposed the Procurement use of Direct Contracting Guidelines method in any contract, regardless of value, shall be sent for the Bank’s prior approval as part of the procurement plan. 1. Pre-qualification: Not applicable. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable. 3. Reference to (if any) Project Operational/Procurement Manual: Not Applicable 4. Any Other Special Procurement Arrangements: (i) PIU may use its own forms of contract for goods/non-consulting services procured under shopping method, which have been reviewed and found acceptable by the Bank; (ii) The Bank may review technical aspects of procurement documents and other non-procurement matters (technical specifications, environmental documents, cost estimate, etc.) related to the procurement activity in questioned, if needed. 5. Summary of the Procurement Packages planned after project effectiveness (including those that are subject to retroactive financing and advance procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank (US$ (yes/no) (Prior / million) Post) 1. Summary of 2,222,222 1 No Prior the ICB (Goods/IT Systems) 2. Summary of 3,310,806 9 No Post the NCB (Goods/IT Systems) 3. Summary of [to be [to be No Post the NCB updated, if updated, if (Non- any] any] consulting Services) 4. Summary of 18,108,526 11 No Post the NCB (Works) 5. Summary of 391,111 8 No Post the Shopping (Goods) 6. Summary of [to be [to be No Post the Shopping updated, if updated, if (Non- any] any] consulting Services) 7. Summary of 481,481 3 No Post the Shopping (Small Works) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Comments No. Cost Preference by Bank (US$ (yes/no) (Prior / million) Post) 8. Summary of [to be [to be No Post the Direct updated , if updated , Contracting any] if any] (Goods/IT systems, Non- Consulting Services and Small Works) B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Selection Method Bank’s Prior Review Selection Method Threshold Requirement No. 1. QCBS (Firms) Applied to all estimated Each contract equal to or value. No threshold. above $500,000 equivalent shall be subject to Bank’s prior review. All other contracts subject to post review. (Prior review from technical perspective of only the draft TOR and draft cost estimate). 2. CQS (Firms) Only for estimated contract No prior review (only post value < $ 300,000 as per review). paragraph 3.7 of the Consultant Guidelines. Ref. Selection Method Bank’s Prior Review Selection Method Threshold Requirement No. 3. Single Source No selection method Each contract equal to or Selection of Firms threshold. Subject to above $500,000 equivalent justification for Singe shall be subject to Bank’s Source Selection of firms as prior review. All other per para. 3.9 and 3.10 of the contracts subject to post Consultant Guidelines. review. (Prior review from technical perspective of only the draft TOR, Justification for use of Single Source Selection method and draft cost estimate, shall be sent for the Bank’s prior approval as part of the procurement plan). 4. Competitive No threshold. No prior review (only post Selection of review), unless contract is Individual equal to or above $200,000. Consultants (comparison of at (Prior review from technical least 3 CVs) perspective of only the draft TOR and draft cost estimate). 5. Single Source No Threshold. No prior review (only post Selection of review), unless contract is Individual Subject to justification for equal to or above $200,000. Consultants single source of individuals as per para. 5.4 of the (Prior review from technical Consultant Guidelines perspective of only the draft TOR, Justification for use of Single Source Selection method together with CV of the recommended candidate and draft cost estimate, shall be sent for the Bank’s prior approval as part of the procurement plan). 2. Shortlist comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Consultants may be hired under Indefinite Delivery Contract (IDCs) or Price Agreement as per paragraph 4.5 of the Consultant Guidelines. 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Type of Estimated Packages/ Review Comments No. of Assignments Cost Positions by Bank Assignments (US$ (Prior / million) Post) 1. Summary of (Time- 18,335,777 18 Prior number of Based/Lumps and Post contracts that ump) will be let under QCBS 2. Summary of (Time-Based 5,813,778 43 Post number of /Lump-Sum) contracts that will be let under other methods (QBS, FBS, LCS and CQS) 3. Summary of (Time-Based 67,407 6 Post number of /Lump-Sum) individual consultant contracts that will be let under competitive selection 4. Summary of (Time-Based [to be [to be Post number of /Lump-Sum) updated, if updated, if individual any] any] consultant contracts that will be let under single- source selection PROCUREMENT Indonesia : Dam Operational Improvement and Safety PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2019-01-03 2019-10-04 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P096532 GPN Date: Project Name: Dam Operational Improvement and Safety Loan / Credit No: COFN / C1460, IBRD / 76690 Executing Agency(ies): Bengawan Solo Major River Basin Development Agency WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BSO-CW-2 / Repair and replace the instrumentation Dam Operational Pending Request for Single Stage - One of V-notch, piezometer, and COFN / C1460 Improvement and Safety Post Open - National 23,333.00 0.00 Implementati 2018-04-21 2018-05-29 2018-12-25 Quotations Envelope Peill Schall on Dawuhan Works and Studies on Dam Dam Operational Pending BSO-CW-1 / Rehabilitation Single Stage - One COFN / C1460 Improvement and Safety Post Request for Bids Open - National 1,820,334.00 0.00 Implementati 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-29 2019-06-23 Works of Ketro Dam Envelope Works and Studies on BSO - CW - 4 / Dam Operational Under Single Stage - One Rehabilitation Works of COFN / C1460 Improvement and Safety Prior Request for Bids Open - National 7,934,926.26 0.00 Implementati 2019-06-25 2019-06-30 2019-08-11 2019-09-10 2019-10-15 2019-10-18 Envelope Pacal Dam Works and Studies on BSO - CW - 3 / Dam Operational Under Single Stage - One Rehabilitation Works of COFN / C1460 Improvement and Safety Prior Request for Bids Open - National 5,947,733.33 0.00 Implementati 2019-09-27 2019-10-02 2019-11-13 2019-12-13 2020-01-17 2021-06-10 Envelope Lalung Dam Works and Studies on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BSO-GD-1 / Provision of Dam Operational Pending Single Stage - One Dregding Pipe and Its COFN / C1460 Improvement and Safety Post Request for Bids Open - National 370,370.00 0.00 Implementati 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2019-02-17 Envelope Equipment Works and Studies on Pending BSO - GD - 2 / Provision Dam Safety Institutional Request for Single Stage - One IBRD / 76690 Post Open - National 13,800.00 0.00 Implementati 2019-07-02 2019-08-27 2020-02-23 of UPB Office Equipment Improvement Quotations Envelope on BSO - GD - 3 / Provision Dam Operational Pending Single Stage - One of BDSF (Basic Dam Safety COFN / C1460 Improvement and Safety Post Request for Bids Open - National 400,000.00 0.00 Implementati 2019-06-27 2019-07-02 2019-08-13 2019-09-12 2019-10-17 2020-04-14 Envelope Facilities) Works and Studies on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BSO-CS-1 / Preparation of DD for Replacement the Dam Operational Consultant Intake Gates, Bonneted Pending COFN / C1460 Improvement and Safety Post Qualification Open - National 185,185.00 0.00 2017-09-25 2017-10-16 2017-11-29 2017-12-29 2018-01-22 2018-09-19 Gates and Rehabilitaion of Implementation Works and Studies Selection Emergency Spillway of Pacal Dam BSO-CS-2 / Design Review for Reparation Works of the Dam Operational Consultant Pending Dam Structure, Crest and COFN / C1460 Improvement and Safety Post Qualification Open - National 92,593.00 0.00 2017-09-25 2017-10-16 2017-11-29 2017-12-29 2018-01-22 2018-08-20 Implementation Its Instrumentation of Works and Studies Selection Lalung Dam BSO-CS-5 / DD for Rehabilitation and Dam Operational Consultant Pending Modernization the COFN / C1460 Improvement and Safety Post Qualification Open - National 74,074.00 0.00 2018-05-01 2018-05-22 2018-07-05 2018-08-04 2018-09-08 2019-05-06 Implementation Hydromechanical and Works and Studies Selection Electrical of Dawuhan Dam BSO-CS-3 / Supervision for Dam Operational Consultant Pending Rehabilitation Works of COFN / C1460 Improvement and Safety Post Qualification Open - National 74,074.00 0.00 2017-09-25 2017-10-16 2017-11-29 2017-12-19 2018-01-08 2019-07-02 Implementation Ketro Dam Works and Studies Selection Operation and Maintenance Consultant BSO-CS-4 / EAP Sangiran, Pending COFN / C1460 Improvement and Capacity Post Qualification Open - National 244,444.00 0.00 2017-09-25 2017-10-16 2017-11-29 2017-12-29 2018-01-22 2018-09-19 Prijetan dan Gondang Implementation Building Selection BSO - CS - 6 / Preparation and Legalization of Dam Operational Quality And Cost- Pending Operation Permit of COFN / C1460 Improvement and Safety Post Open - National 200,000.00 0.00 2019-06-17 2019-07-08 2019-08-21 2019-09-18 2019-10-18 2019-11-22 2019-12-27 2020-12-26 Based Selection Implementation Dawuhan, Krisak, and Works and Studies Gonggang Dams BSO - CS - 18 / Preparation and Legalization Dam Operational Quality And Cost- Open - Pending of Operation Permit of COFN / C1460 Improvement and Safety Post 407,407.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 Based Selection International Implementation Ngancar, Kembangan and Works and Studies Wonogiri Dams BSO - CS - 21 / Preparation and Legalization Dam Operational Quality And Cost- Open - Pending of Operation Permit of Song COFN / C1460 Improvement and Safety Post 355,556.00 0.00 2019-06-25 2019-07-16 2019-08-06 2019-09-03 2019-10-03 2019-11-07 2019-12-12 2020-12-11 Based Selection International Implementation Putri, Nawangan and Works and Studies Parangjoho Dams BSO - CS - 22 / Preparation and Legalization Dam Operational of Operation Permit of Quality And Cost- Open - Pending COFN / C1460 Improvement and Safety Post 370,370.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 Cengklik, Delingan, and Based Selection International Implementation Works and Studies Ketro Dams and the Pacal Dam Physical Model Test BSO - CS - 23 / Preparation and Legalization Dam Operational Quality And Cost- Open - Pending of Operation Permit of COFN / C1460 Improvement and Safety Post 444,444.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 Based Selection International Implementation Pondok, Saradan, Gondang Works and Studies and Prijetan Dams BSO - CS - 19 / Preparation and Legalization Dam Operational Quality And Cost- Open - Pending of Operation Permit of COFN / C1460 Improvement and Safety Post 370,370.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 Based Selection International Implementation Sangiran and Telaga Pasir Works and Studies Dams Page 2 BSO - CS - 20 / Preparation and Legalization Dam Operational Quality And Cost- Open - Pending of Operation Permit of COFN / C1460 Improvement and Safety Post 370,370.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 Based Selection International Implementation Kedung Brubus and Kedung Works and Studies Bendo Dams BSO - CS - 17 / SID Dam Operational Sedimentation Conservation Quality And Cost- Open - Pending COFN / C1460 Improvement and Safety Post 320,000.00 0.00 2019-06-26 2019-07-17 2019-08-30 2019-09-27 2019-10-27 2019-12-01 2020-01-05 2021-01-04 of 6 Reservoirs and UKL + Based Selection International Implementation Works and Studies UPL BSO - CS - 7 / Supervision Dam Operational Quality And Cost- Under of Rehabilitation Works of COFN / C1460 Improvement and Safety Post Open - National 237,909.33 0.00 2019-09-27 2019-10-18 2019-12-01 2019-12-29 2020-01-28 2020-03-03 2020-04-07 2021-08-30 Based Selection Implementation Lalung Dam Works and Studies BSO - CS - 8 / Supervision Dam Operational Quality And Cost- Open - Pending of Rehabilitation Works of COFN / C1460 Improvement and Safety Post 317,397.06 0.00 2019-10-05 2019-10-26 2019-12-09 2020-01-06 2020-02-05 2020-03-11 2020-04-15 2021-12-06 Based Selection International Implementation Pacal Dam Works and Studies INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3