Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) LB-Environmental Pollution Abatement Project (P143594) MIDDLE EAST AND NORTH AFRICA | Lebanon | Environment & Natural Resources Global Practice | IBRD/IDA | Financial Intermediary Loan | FY 2015 | Seq No: 4 | ARCHIVED on 14-Jun-2016 | ISR23903 | Implementing Agencies: Ministry of Environment, Central Bank Key Dates Key Project Dates Bank Approval Date:01-Aug-2014 Effectiveness Date:28-Jan-2016 Planned Mid Term Review Date:30-Mar-2017 Actual Mid-Term Review Date:-- Original Closing Date:31-Mar-2021 Revised Closing Date:31-Mar-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objectives of the project are to assist the Borrower in: (a) reducing industrial pollution in targeted Industrial Enterprises; and (b) strengthening the monitoring and enforcement capabilities of the MOE. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name A. Technical Assistance (parallel financing):(Cost $3.00 M) B. Investment Sub-projects (IBRD):(Cost $15.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  High  High Implementation Status and Key Decisions 6/14/2016 Page 1 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) The project was ratified by Parliament on November 13, 2015 and become effective on January 28, 2016. Three sub-projects were financed under the BDL financing window and are progressing and additional sub-projects have been identified and in the pipeline. 6/14/2016 Page 2 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  High  High Macroeconomic  --  High  High Sector Strategies and Policies  --  Moderate  Moderate Technical Design of Project or Program  --  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  --  High  High Fiduciary  --  High  High Environment and Social  --  Moderate  Moderate Stakeholders  --  High  High Other  --  --  -- Overall  --  High  High 6/14/2016 Page 3 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) Results Project Development Objective Indicators PHINDPDOTBL  Enterprises financed through the project that conform to the environmental compliance decree (8471-2012) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDPDOTBL  Enterprises that would reduce their BOD discharges (t) by more than 50% (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDPDOTBL  Enterprises that would reduce their air pollutants (PM10) by more than 50% (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDPDOTBL  Regularly published monitoring reports covering environmental compliance of participating Enterprises by MOE (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 Overall Comments 6/14/2016 Page 4 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) Intermediate Results Indicators PHINDIRITBL  Participating banks (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  Enterprises borrowing (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  Sub-loans (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  Sub-loans (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 14.96 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 6/14/2016 Page 5 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) PHINDIRITBL  Establishment of Guidelines for Sector EIA (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 9.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  People trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5000.00 Date 01-Aug-2014 30-Nov-2015 28-May-2016 30-Sep-2020 PHINDIRITBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 51.00 6/14/2016 Page 6 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) PHINDIRITBL  Particulate matter reduction achieved under the project (Microgram/m3, Core) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- -- Date -- -- -- -- Comments Baselines and targets will be determined during project implementation once the sub-projects have been identified and are under implementation. PHINDIRITBL  Number of people with exposure to PM10 in the area of the project (Number, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- -- PHINDIRITBL  Voume(mass) of COD pollution load reduction achieved under the project (Tones/year, Core) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- -- Date -- -- -- -- Comments Baselines and targets will be determined during project implementation once the sub-projects have been identified and are under implementation. PHINDIRITBL  Industrial or municipal solid waste reduced or recycled under the project (Tones/year, Core) Baseline Actual (Previous) Actual (Current) End Target Value -- -- -- -- Date -- -- -- -- Comments 6/14/2016 Page 7 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) Baselines and targets will be determined during project implementation once the sub-projects have been identified and are under implementation. Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P143594 IBRD-84100 Effective USD 15.00 15.00 0.00 0.04 14.96 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P143594 IBRD-84100 Effective 01-Aug-2014 24-Oct-2014 28-Jan-2016 31-Mar-2021 31-Mar-2021 Cumulative Disbursements 6/14/2016 Page 8 of 9 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report LB-Environmental Pollution Abatement Project (P143594) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/14/2016 Page 9 of 9 Public Disclosure Copy